ONSHORE WIND · MISO

Onshore wind project J499, Adair County

Onshore wind project J499, Adair County is a 340 MW onshore wind request built and operating in the MISO interconnection queue, in Adair County, Iowa.

Queue statusOperating
  1. PlanningQueued Nov 2015 (completed)
  2. ConsentedFeb 2019 (completed)
  3. Construction (completed)
  4. OperatingMar 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J499
Grid region
MISO (Midcontinent)
Connection point (POI)
MEC 345 kV Fallow-Grimes line (18 miles east of Fallow substation)
Location
Adair County, Iowa
Technology
Wind: 340 MW
Total requested
340 MW
Study phase
GIA
Queue status
Operational
Entered queue
13 November 2015
Agreement signed
8 February 2019
Proposed online date
March 2016
Came online
March 2016

Location

Marker shows the centre of Adair County; the queue data does not give exact sites.

Power plants in Iowa · Transmission lines in Iowa

Other requests in Adair County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem