United States › Grid › Interconnection queues › Idaho

SOLAR + STORAGE · WEST

Solar + storage project 656, Jerome County

Solar + storage project 656, Jerome County is a 300 MW solar + storage request suspended in the West interconnection queue, in Jerome County, Idaho, connecting to Idaho Power Company.

Queue statusPaused / redesign
  1. PlanningQueued May 2022 (current stage)
  2. ConsentedNov 2023 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
656
Grid region
West (non-ISO utilities)
Utility / transmission owner
Idaho Power Company
Developer
Red Bridge Energy, LLC
Connection point (POI)
Midpoint 345kV Substation
Location
Jerome County, Idaho
Technology
Solar: 300 MW · Battery
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Suspended
Entered queue
13 May 2022
Agreement signed
2 November 2023
Proposed online date
September 2027

Location

Marker shows the centre of Jerome County; the queue data does not give exact sites.

Power plants in Idaho · Transmission lines in Idaho

Other requests in Jerome County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem