OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 474

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 474 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J445, Gratiot County
Battery storage
2.0 MWWithdrawn / abandoned Gratiot, MIMISO May 2015target 2017
Battery storage project AH1-143, Henrico County
Battery storage
2.0 MWWithdrawn / abandoned Henrico, VAPJM Aug 2021target 2024
Solar project AF1-110
Solar
2.0 MWWithdrawn / abandoned NJPJM Sep 2019
Battery storage project 20200720001, Lexington County
Battery storage
2.0 MWWithdrawn / abandoned Lexington, SCSoutheast target 2021
Other project G0483, Skamania County
Other
2.0 MWWithdrawn / abandoned Skamania, WAWest May 2013target 2014
Hydro project GEN-2015-007IS
Hydro
2.0 MWWithdrawn / abandoned SPP Nov 2015
Hydro project 339, Washington County
Hydro
2.0 MWWithdrawn / abandoned Washington, UTWest Jun 2010target 2020
Solar project C3-074, Millard County
Solar
2.0 MWWithdrawn / abandoned Millard, UTWest May 2023target 2023
Solar project Y1-045, Howard County
Solar
2.0 MWWithdrawn / abandoned Howard, MDPJM Mar 2012target 2017
BU-Union
Solar + storage
2.0 MWWithdrawn / abandoned Bucks, PAPJM Mar 2020target 2023
Solar project 615, Washington County
Solar
2.0 MWWithdrawn / abandoned Washington, UTWest Aug 2014target 2015
Hydro project 834, Klamath County
Hydro
2.0 MWWithdrawn / abandoned Klamath, ORWest Dec 2016target 2017
Solar project AE2-097, Burlington County
Solar
2.0 MWWithdrawn / abandoned Burlington, NJPJM Feb 2019target 2020
Other project U4-047, Erie County
Other
2.0 MWWithdrawn / abandoned Erie, PAPJM Jan 2009target 2011
Solar project X2-024, Salem County
Solar
2.0 MWWithdrawn / abandoned Salem, NJPJM May 2011target 2011
Battery storage project AA1-105, Gloucester County
Battery storage
2.0 MWWithdrawn / abandoned Gloucester, NJPJM Oct 2014target 2015
Solar + Battery Storage
Solar + storage
2.0 MWWithdrawn / abandoned Berkshire, MAISO-NE May 2020target 2022
Battery storage project 20191213001, Hampton County
Battery storage
2.0 MWWithdrawn / abandoned Hampton, SCSoutheast target 2020
Cayuta Add-on
Battery storage · Nexamp Solar
2.0 MWWithdrawn / abandoned Schuyler, NYNYISO Oct 2023
Solar project 280, Klamath County
Solar
2.0 MWWithdrawn / abandoned Klamath, ORWest Jul 2009target 2010
Solar project 19176, Marlboro County
Solar
2.0 MWWithdrawn / abandoned Marlboro, SCSoutheast Nov 2017
Fredon Solar Farm
Solar
2.0 MWWithdrawn / abandoned Sussex, NJPJM Apr 2012target 2015
Warsaw Solar
Solar · ESA Solar NY, LLC
2.0 MWWithdrawn / abandoned Wyoming, NYNYISO Nov 2014
Solar project 727, Klamath County
Solar
2.0 MWWithdrawn / abandoned Klamath, ORWest Feb 2016target 2018
Solar project 972, Klamath County
Solar
2.0 MWWithdrawn / abandoned Klamath, ORWest Nov 2017target 2018
Augusta E. Side 115 kV SS - Augusta Area Study
Solar
2.0 MWWithdrawn / abandoned Kennebec, MEISO-NE Oct 2020target 2024
Solar project 197, Gilliam County
Solar · Columbia Energy Partners, LLC
2.0 MWWithdrawn / abandoned Gilliam, ORWest Feb 2008target 2011
Grove City Road 12kV
Solar
2.0 MWWithdrawn / abandoned Butler, PAPJM Apr 2010target 2015
Solar project 19170, Marlboro County
Solar
2.0 MWWithdrawn / abandoned Marlboro, SCSoutheast Oct 2017
Solar project 19603, Greenwood County
Solar
2.0 MWWithdrawn / abandoned Greenwood, SCSoutheast Jan 2018
Washington County Renewable Energy Project
Other
2.0 MWWithdrawn / abandoned Washington, MDPJM Jun 2011target 2013
Solar project AC1-032, Will County
Solar
2.0 MWWithdrawn / abandoned Will, ILPJM Aug 2016target 2017
Highland/Park St 115 kV SS - Midcoast Area DG Study
Solar
2.0 MWWithdrawn / abandoned Knox, MEISO-NE Oct 2023target 2024
Other project AB1-185
Other
2.0 MWWithdrawn / abandoned PJM Nov 2015target 2016
Solar + Battery Storage
Solar + storage
2.0 MWWithdrawn / abandoned Franklin, MAISO-NE Apr 2021target 2022
Solar project Y3-095, Queen Anne's County
Solar
2.0 MWWithdrawn / abandoned Queen Anne's, MDPJM Apr 2013target 2013
Solar project W3-073, Cape May County
Solar
2.0 MWWithdrawn / abandoned Cape May, NJPJM Sep 2010target 2011
Cineguilla Project
Solar · enXco Dev. Corp.
2.0 MWWithdrawn / abandoned Santa Fe, NMWest Oct 2008target 2014
NO-Oakes
Solar + storage
2.0 MWWithdrawn / abandoned Northumberland, PAPJM Mar 2020target 2023
Solar project TCS-15, Yakima County
Solar · OneEnergy Development, LLC
2.0 MWWithdrawn / abandoned Yakima, WAWest Oct 2018target 2024
Solar project 19139, Dillon County
Solar
2.0 MWWithdrawn / abandoned Dillon, SCSoutheast Oct 2017
Fauquier County Landfill Units 1 & 2
Other
2.0 MWWithdrawn / abandoned Fauquier, VAPJM Oct 2012target 2016
Solar project 494, Millard County
Solar · Bevan's Point Holdings, LLC
2.0 MWWithdrawn / abandoned Millard, UTWest Mar 2013target 2013
West Amwell Mason Supply Solar Farm
Solar
2.0 MWWithdrawn / abandoned Hunterdon, NJPJM Jul 2010target 2017
Solar project AH2-067, Cook County
Solar
2.0 MWWithdrawn / abandoned Cook, ILPJM Jan 2022target 2023
Solar project W3-114, Venango County
Solar
2.0 MWWithdrawn / abandoned Venango, PAPJM Oct 2010target 2011
Verogy - Tripp RD
Solar
2.0 MWWithdrawn / abandoned Hartford, CTISO-NE Dec 2021target 2023
Nuclear project H01, Columbia County
Nuclear
2.0 MWWithdrawn / abandoned Columbia, PAPJM Jul 2001target 2003
Hamilton Sunstrand
Solar
2.0 MWWithdrawn / abandoned Hartford, CTISO-NE Dec 2021target 2023
Solar project W3-015, Atlantic County
Solar
2.0 MWWithdrawn / abandoned Atlantic, NJPJM Aug 2010target 2011
Page 474 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)