HYDRO Β· SPP

Hydro project GEN-2015-007IS

Hydro project GEN-2015-007IS is a 2.0 MW hydro request withdrawn in the SPP interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2015 (completed)
  2. Withdrawn / abandonedApr 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2015-007IS
Grid region
SPP (Southwest Power Pool)
Technology
Hydro: 2.0 MW
Total requested
2.0 MW
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
25 November 2015
Withdrawn
April 2016

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem