United States β€Ί Grid β€Ί Interconnection queues β€Ί Connecticut

SOLAR Β· ISO-NE

Hamilton Sunstrand

Hamilton Sunstrand is a 2.0 MW solar request withdrawn in the ISO-NE interconnection queue, in Hartford County, Connecticut, connecting to NU.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2021 (completed)
  2. Withdrawn / abandonedJun 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1205
Grid region
ISO-NE (New England)
Utility / transmission owner
NU
Connection point (POI)
Windsor Locks 14K
Location
Hartford County, Connecticut
Technology
Solar: 2.0 MW
Total requested
2.0 MW
Queue status
Withdrawn
Entered queue
30 December 2021
Proposed online date
April 2023
Withdrawn
June 2025

Location

No county location in the queue data.

Power plants in Connecticut Β· Transmission lines in Connecticut

Other requests in Hartford County