Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 467 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project O34, Frederick County
Gas
3.0 MWWithdrawn / abandoned Frederick, MDPJM Jun 2005target 2006
Solar project 194, Big Horn County
Solar
3.0 MWWithdrawn / abandoned Big Horn, MTWest Feb 2015target 2016
Solar project V4-062, Salem County
Solar
3.0 MWWithdrawn / abandoned Salem, NJPJM Jan 2010target 2010
Solar project 224, Cascade County
Solar
3.0 MWWithdrawn / abandoned Cascade, MTWest Nov 2015target 2016
Solar project 518, Washington County
Solar
3.0 MWWithdrawn / abandoned Washington, UTWest Oct 2013target 2015
DA-Matamoras
Solar + storage
3.0 MWWithdrawn / abandoned Dauphin, PAPJM Mar 2020target 2023
Solar project V4-044, Salem County
Solar
3.0 MWWithdrawn / abandoned Salem, NJPJM Dec 2009target 2010
Other project 5, Ada County
Other
3.0 MWWithdrawn / abandoned Ada, IDWest Mar 2001target 2001
Solar project 486, Beaver County
Solar
3.0 MWWithdrawn / abandoned Beaver, UTWest Mar 2013target 2014
Solar project 201, Broadwater County
Solar
3.0 MWWithdrawn / abandoned Broadwater, MTWest Feb 2015target 2016
Solar project AG2-374, Tioga County
Solar
3.0 MWWithdrawn / abandoned Tioga, PAPJM Mar 2021target 2023
Other project X4-042, Fayette County
Other
3.0 MWWithdrawn / abandoned Fayette, PAPJM Jan 2012target 2013
Glidepath Ventures
Solar + storage
3.0 MWWithdrawn / abandoned Northumberland, PAPJM Mar 2020target 2023
Onshore wind project GEN-2015-028, Kay County
Onshore wind
3.0 MWWithdrawn / abandoned Kay, OKSPP Apr 2015target 2016
Solar project AG2-071, Cumberland County
Solar
3.0 MWWithdrawn / abandoned Cumberland, NJPJM Dec 2020target 2021
Solar + storage project AH2-183, Ogle County
Solar + storage
3.0 MWWithdrawn / abandoned Ogle, ILPJM Mar 2022target 2024
Solar + storage project 1071, Yakima County
Solar + storage
3.0 MWWithdrawn / abandoned Yakima, WAWest Oct 2018target 2020
Putnam Pike - NG WRI DG Area Study #2 <5 MW
Solar
3.0 MWWithdrawn / abandoned Providence, RIISO-NE Aug 2020target 2021
Solar project 258, Phillips County
Solar
3.0 MWWithdrawn / abandoned Phillips, MTWest Feb 2016target 2016
PA York Garber 1
Solar
3.0 MWWithdrawn / abandoned York, PAPJM Jan 2020target 2022
Solar + storage project AH2-175
Solar + storage
3.0 MWWithdrawn / abandoned PJM Mar 2022target 2024
Solar project AG2-021, York County
Solar
3.0 MWWithdrawn / abandoned York, PAPJM Oct 2020target 2021
Citron Storage
Battery storage
3.0 MWWithdrawn / abandoned Wicomico, MDPJM Mar 2020target 2023
Solar project 535, Millard County
Solar
3.0 MWWithdrawn / abandoned Millard, UTWest Nov 2013target 2014
Solar project C3-178, Klamath County
Solar
3.0 MWWithdrawn / abandoned Klamath, ORWest May 2023target 2024
Onshore wind project G584, Pipestone County
Onshore wind
3.0 MWWithdrawn / abandoned Pipestone, MNMISO Dec 2005target 2007
Solar project 1061, Klamath County
Solar
3.0 MWWithdrawn / abandoned Klamath, ORWest Aug 2018target 2019
FA-Rockwell
Solar + storage
3.0 MWWithdrawn / abandoned Fayette, PAPJM Mar 2020target 2024
Solar project 238, Judith Basin County
Solar
3.0 MWWithdrawn / abandoned Judith Basin, MTWest Dec 2015target 2016
Solar project 1098, Polk County
Solar
3.0 MWWithdrawn / abandoned Polk, ORWest Jan 2019target 2020
Solar project AB1-165, Burlington County
Solar
3.0 MWWithdrawn / abandoned Burlington, NJPJM Oct 2015target 2016
Solar + storage project C2-88, Linn County
Solar + storage
3.0 MWWithdrawn / abandoned Linn, ORWest May 2022target 2024
Solar project 1017, Umatilla County
Solar
3.0 MWWithdrawn / abandoned Umatilla, ORWest Mar 2018target 2020
Solar project 189, Lewis And Clark County
Solar
3.0 MWWithdrawn / abandoned Lewis And Clark, MTWest Feb 2015target 2016
Solar project 476, Beaver County
Solar
3.0 MWWithdrawn / abandoned Beaver, UTWest Mar 2013target 2014
Solar project 1097, Polk County
Solar
3.0 MWWithdrawn / abandoned Polk, ORWest Jan 2019target 2020
Solar project 220, Cascade County
Solar
3.0 MWWithdrawn / abandoned Cascade, MTWest Nov 2015target 2016
Solar project 185, Missoula County
Solar
3.0 MWWithdrawn / abandoned Missoula, MTWest Feb 2015target 2016
Battery storage project W3-093, Berks County
Battery storage
3.0 MWWithdrawn / abandoned Berks, PAPJM Oct 2010target 2011
Solar project 477, Iron County
Solar
3.0 MWWithdrawn / abandoned Iron, UTWest Mar 2013target 2014
Lambie Energy Center
Solar
3.0 MWWithdrawn / abandoned Solano, CACAISO Mar 2011target 2013
Solar project 728, Umatilla County
Solar
3.0 MWWithdrawn / abandoned Umatilla, ORWest Feb 2016target 2017
Solar project 526, Emery County
Solar
3.0 MWWithdrawn / abandoned Emery, UTWest Oct 2013target 2014
Solar project C2-100, Linn County
Solar
3.0 MWWithdrawn / abandoned Linn, ORWest May 2022target 2024
Solar project 388, Iron County
Solar
3.0 MWWithdrawn / abandoned Iron, UTWest May 2011target 2011
Solar project C2-85, Linn County
Solar
3.0 MWWithdrawn / abandoned Linn, ORWest May 2022target 2024
Solar project C4-120, Jefferson County
Solar
3.0 MWWithdrawn / abandoned Jefferson, ORWest May 2024target 2025
Solar plus Battery
Solar + storage
3.0 MWWithdrawn / abandoned Hampshire, MAISO-NE Feb 2022target 2022
Solar project 304, Judith Basin County
Solar
3.0 MWWithdrawn / abandoned Judith Basin, MTWest Nov 2016target 2020
Solar project 222, Cascade County
Solar
3.0 MWWithdrawn / abandoned Cascade, MTWest Nov 2015target 2020
Page 467 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)