SOLAR Β· PJM

Solar project AG2-021, York County

Solar project AG2-021, York County is a 3.0 MW solar request withdrawn in the PJM interconnection queue, in York County, Pennsylvania, connecting to ME.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2020 (completed)
  2. Withdrawn / abandonedOct 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-021
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ME
Connection point (POI)
Crossroads 13.2 kV
Location
York County, Pennsylvania
Technology
Solar: 3.0 MW
Total requested
3.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
23 October 2020
Proposed online date
December 2021
Withdrawn
October 2024

Location

Marker shows the centre of York County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in York County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem