SOLAR Β· PJM

Solar project AG2-071, Cumberland County

Solar project AG2-071, Cumberland County is a 3.0 MW solar request withdrawn in the PJM interconnection queue, in Cumberland County, New Jersey, connecting to AEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2020 (completed)
  2. Withdrawn / abandonedJan 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-071
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEC
Connection point (POI)
Cumberland 12 kV
Location
Cumberland County, New Jersey
Technology
Solar: 3.0 MW
Total requested
3.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
31 December 2020
Proposed online date
December 2021
Withdrawn
January 2022

Location

Marker shows the centre of Cumberland County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Cumberland County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem