Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 435 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AB1-067, Orange County
Solar
10.0 MWWithdrawn / abandoned Orange, VAPJM Aug 2015target 2016
Eversource Group @ Valley 715
Solar + storage
10.0 MWWithdrawn / abandoned Barnstable, MAISO-NE Apr 2020target 2023
Solar project AH1-499, Mercer County
Solar
10.0 MWWithdrawn / abandoned Mercer, PAPJM Sep 2021target 2024
Solar project W3-086, New Castle County
Solar
10.0 MWWithdrawn / abandoned New Castle, DEPJM Oct 2010target 2011
Gas project 130, Yellowstone County
Gas
10.0 MWWithdrawn / abandoned Yellowstone, MTWest Dec 2010target 2012
Solar project Z1-077, Worcester County
Solar
10.0 MWWithdrawn / abandoned Worcester, MDPJM Oct 2013target 2018
Onshore wind project 263, Umatilla County
Onshore wind · Pine City Windfarm, LLC
10.0 MWWithdrawn / abandoned Umatilla, ORWest Mar 2009target 2009
Solar project 4538, Dillon County
Solar
10.0 MWWithdrawn / abandoned Dillon, SCSoutheast Oct 2015
Geothermal project G0821, Cassia County
Geothermal
10.0 MWWithdrawn / abandoned Cassia, IDWest Nov 2022target 2025
Solar project W3-167, Chester County
Solar
10.0 MWWithdrawn / abandoned Chester, PAPJM Oct 2010target 2011
Broadway Solar Farm
Solar
10.0 MWWithdrawn / abandoned Warren, NJPJM Oct 2010target 2017
Quakertown Solar Farm #2
Solar
10.0 MWWithdrawn / abandoned Hunterdon, NJPJM Jun 2011target 2016
Solar + storage project AI1-197, Adams County
Solar + storage
10.0 MWWithdrawn / abandoned Adams, PAPJM Sep 2022target 2024
Railroad Avenue Energy Storage
Battery storage
10.0 MWWithdrawn / abandoned Hudson, NJPJM Apr 2020target 2025
Solar project X1-051, Burlington County
Solar
10.0 MWWithdrawn / abandoned Burlington, NJPJM Mar 2011target 2012
Gas project 95, Harney County
Gas
9.9 MWWithdrawn / abandoned Harney, ORWest Aug 2003target 2005
Onshore wind project N20, Boone County
Onshore wind
9.9 MWWithdrawn / abandoned Boone, ILPJM Jan 2005target 2005
Gas project C11, Juniata County
Gas
9.9 MWWithdrawn / abandoned Juniata, PAPJM Feb 2000
Wieland Substation BESS Unit 1
Battery storage · Telios Quinlan Energy One, LLC
9.9 MWWithdrawn / abandoned ERCOT Mar 2025target 2026
Other project I16, Butler County
Other
9.9 MWWithdrawn / abandoned Butler, PAPJM Jul 2002target 2003
Onshore wind project 142, Wheatland County
Onshore wind
9.9 MWWithdrawn / abandoned Wheatland, MTWest Jun 2011target 2012
Hydro project V3-047, Braxton County
Hydro
9.9 MWWithdrawn / abandoned Braxton, WVPJM Sep 2009target 2010
Hydro project W1-080, Braxton County
Hydro
9.9 MWWithdrawn / abandoned Braxton, WVPJM Apr 2010target 2012
Other project I19, Westmoreland County
Other
9.9 MWWithdrawn / abandoned Westmoreland, PAPJM Jul 2002target 2003
Other project I15, Somerset County
Other
9.9 MWWithdrawn / abandoned Somerset, PAPJM Jul 2002target 2003
Solar project AG2-673, Baltimore County
Solar
9.9 MWWithdrawn / abandoned Baltimore, MDPJM Mar 2021target 2022
Onshore wind project 143, Wheatland County
Onshore wind
9.9 MWWithdrawn / abandoned Wheatland, MTWest Jun 2011target 2012
Moore Field BESS
Battery storage · SBESS TX11 LLC
9.9 MWWithdrawn / abandoned ERCOT Jul 2023target 2024
Solar project 618, Klamath County
Solar
9.9 MWWithdrawn / abandoned Klamath, ORWest Sep 2014target 2016
Raymond 115 kV SS - Raymond Area DG Study
Solar
9.9 MWWithdrawn / abandoned Cumberland, MEISO-NE Sep 2023target 2025
Onshore wind project 141, Wheatland County
Onshore wind
9.9 MWWithdrawn / abandoned Wheatland, MTWest Jun 2011target 2012
Other project L20, Berks County
Other
9.9 MWWithdrawn / abandoned Berks, PAPJM Jan 2004target 2005
Onshore wind project G679, Mclean County
Onshore wind
9.9 MWWithdrawn / abandoned Mclean, ILMISO Sep 2006target 2012
Onshore wind project 144, Wheatland County
Onshore wind
9.9 MWWithdrawn / abandoned Wheatland, MTWest Jun 2011target 2012
Other project G373, Murray County
Other
9.9 MWWithdrawn / abandoned Murray, MNMISO Oct 2003target 2004
Gas project B22, Baltimore City County
Gas
9.9 MWWithdrawn / abandoned Baltimore City, MDPJM Aug 1999
Onshore wind project L11, Somerset County
Onshore wind
9.9 MWWithdrawn / abandoned Somerset, PAPJM Dec 2003target 2005
Solar + storage project AH2-012, Halifax County
Solar + storage
9.9 MWWithdrawn / abandoned Halifax, VAPJM Oct 2021target 2022
Solar project AC1-095, New Castle County
Solar
9.9 MWWithdrawn / abandoned New Castle, DEPJM Oct 2016target 2018
Other project I17, Berks County
Other
9.9 MWWithdrawn / abandoned Berks, PAPJM Jul 2002target 2003
Pueblo BESS
Battery storage · SBESS TX 9 LLC
9.9 MWWithdrawn / abandoned ERCOT Jun 2023target 2024
Onshore wind project 208, Malheur County
Onshore wind
9.9 MWWithdrawn / abandoned Malheur, ORWest Nov 2007target 2009
North McAllen BESS
Battery storage · SBESS TX 3, LLC
9.9 MWWithdrawn / abandoned ERCOT Jan 2023target 2024
Redwood Landfill
Other
9.9 MWWithdrawn / abandoned Marin, CACAISO Oct 2008target 2014
Other project I20, Allegheny County
Other
9.9 MWWithdrawn / abandoned Allegheny, PAPJM Jul 2002target 2003
Solar project AB1-104, Camden County
Solar
9.9 MWWithdrawn / abandoned Camden, NJPJM Oct 2015target 2016
Gas project K16, Berks County
Gas
9.9 MWWithdrawn / abandoned Berks, PAPJM Jul 2003target 2004
Other project I18, Allegheny County
Other
9.9 MWWithdrawn / abandoned Allegheny, PAPJM Jul 2002target 2003
Group @ Montigue - WMA ASO
Solar + storage
9.9 MWWithdrawn / abandoned Franklin, MAISO-NE Jan 2022target 2023
Solar + storage project AI1-196, Fayette County
Solar + storage
9.8 MWWithdrawn / abandoned Fayette, PAPJM Sep 2022target 2024
Page 435 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)