United States βΊ Grid βΊ Interconnection queues
BATTERY STORAGE Β· ERCOTPueblo BESS
Pueblo BESS is a 9.9 MW battery storage request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 24INR0581
- Grid region
- ERCOT (Texas)
- Developer
- SBESS TX 9 LLC
- Connection point (POI)
- Load: 9.9MW_x000D_ Load Name or Load Transformer name: 138_12_2_x000D_ PTI Bus #: 8273_x000D_ Transmission-level voltage (high side kV): 138
- Technology
- Battery: 9.9 MW
- Total requested
- 9.9 MW
- Study phase
- No MRD
- Queue status
- Withdrawn
- Entered queue
- 14 June 2023
- Proposed online date
- October 2024
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem