🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Jersey

SOLAR · PJM

Quakertown Solar Farm #2

Quakertown Solar Farm #2 is a 10.0 MW solar request withdrawn in the PJM interconnection queue, in Hunterdon County, New Jersey, connecting to JCPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2011 (completed)
  2. Withdrawn / abandonedJul 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
X2-054
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
JCPL
Connection point (POI)
Franklin
Location
Hunterdon County, New Jersey
Technology
Solar: 10.0 MW
Total requested
10.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Withdrawn
Entered queue
30 June 2011
Proposed online date
April 2016
Withdrawn
July 2016

Location

Marker shows the centre of Hunterdon County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Hunterdon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem