Milford Solar Farm

Milford Solar Farm is a 7.5 MW solar request built and operating in the PJM interconnection queue, in Hunterdon County, New Jersey, connecting to JCPL.

Queue statusOperating
  1. PlanningQueued Mar 2018 (completed)
  2. ConsentedDec 2019 (completed)
  3. Construction (completed)
  4. OperatingSep 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AD2-070
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
JCPL
Connection point (POI)
Gilbert-Morris Park 34.5kV
Location
Hunterdon County, New Jersey
Technology
Solar: 7.5 MW
Total requested
7.5 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
12 March 2018
Agreement signed
9 December 2019
Proposed online date
June 2020
Came online
September 2019

Location

Marker shows the centre of Hunterdon County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Hunterdon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem