United States βΊ Grid βΊ Interconnection queues
BATTERY STORAGE Β· ERCOTMoore Field BESS
Moore Field BESS is a 9.9 MW battery storage request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 24INR0598
- Grid region
- ERCOT (Texas)
- Developer
- SBESS TX11 LLC
- Connection point (POI)
- Transformer - XFMR #2 _x000D_ Station Code - MOORE_FL_x000D_ Load Name - LD2_x000D_ PTI Bus # - 80117_x000D_ Transmission Voltage - 138
- Technology
- Battery: 9.9 MW
- Total requested
- 9.9 MW
- Study phase
- No MRD
- Queue status
- Withdrawn
- Entered queue
- 12 July 2023
- Proposed online date
- October 2024
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem