United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 417

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 417 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project W3-168, Adams County
Solar
15.0 MWWithdrawn / abandoned Adams, PAPJM Oct 2010target 2012
Battery storage project AH1-468, York County
Battery storage
15.0 MWWithdrawn / abandoned York, PAPJM Sep 2021target 2023
Centerville Pike Solar
Solar
15.0 MWWithdrawn / abandoned City Of Chesapeake, VAPJM Aug 2016target 2018
Tracy Desalination And Green Energy Project
Other
15.0 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2012target 2014
Hydro project 51, Teton County
Hydro
15.0 MWWithdrawn / abandoned Teton, MTWest Aug 2006target 2009
Solar project AG2-132, Van Buren County
Solar · CP McDonald Station LLC
15.0 MWWithdrawn / abandoned Van Buren, MIPJM Feb 2021target 2026
Solar project Y1-060, Hertford County
Solar
15.0 MWWithdrawn / abandoned Hertford, NCPJM Apr 2012target 2013
Turning Point Solar
Solar
15.0 MWWithdrawn / abandoned Noble, OHPJM Oct 2010target 2018
Gas project GEN-2012-010, Yoakum County
Gas
15.0 MWWithdrawn / abandoned Yoakum, TXSPP Mar 20122014
Orient Point BESS
Battery storage · Saturn Energy Storage LLC
15.0 MWWithdrawn / abandoned Suffolk, NYNYISO Dec 2021
Solar + storage project J2778, Miami County
Solar + storage
15.0 MWWithdrawn / abandoned Miami, INMISO Sep 2022target 2025
Bio Verde PV - Kettleman 1
Solar
15.0 MWWithdrawn / abandoned Kings, CACAISO Feb 2010target 2012
Solar project AH1-346, Rockingham County
Solar
15.0 MWWithdrawn / abandoned Rockingham, VAPJM Sep 2021target 2023
Solar project AG2-201, Clarion County
Solar
15.0 MWWithdrawn / abandoned Clarion, PAPJM Mar 2021target 2023
Bellegrove Solar
Solar
15.0 MWWithdrawn / abandoned Lebanon, PAPJM Sep 2019target 2027
Solar project W3-087, Kent County
Solar
15.0 MWWithdrawn / abandoned Kent, DEPJM Oct 2010target 2011
Gas project Q35, Coshocton County
Gas
15.0 MWWithdrawn / abandoned Coshocton, OHPJM Apr 2006target 2007
Onshore wind project GEN-2014-022, Kay County
Onshore wind
15.0 MWWithdrawn / abandoned Kay, OKSPP Sep 2014target 2015
Centre Hall
Solar
15.0 MWWithdrawn / abandoned Centre, PAPJM Sep 2019target 2026
Solar project IC-271, Laurens County
Solar
15.0 MWWithdrawn / abandoned Laurens, GASoutheast Nov 2012
Solar project AD2-117, Berks County
Solar
15.0 MWWithdrawn / abandoned Berks, PAPJM Mar 2018target 2020
Watt Energy Storage
Battery storage
15.0 MWWithdrawn / abandoned Solano, CACAISO Apr 2014target 2017
NW-Rocky Ford Solar
Solar · NW-Rocky Ford LLC
15.0 MWWithdrawn / abandoned Nottoway, VAPJM Sep 2020target 2021
Other project 263, Pontotoc County
Other
15.0 MWWithdrawn / abandoned Pontotoc, MSSoutheast Dec 2014
Coso #1
Geothermal
15.0 MWWithdrawn / abandoned Inyo, CACAISO May 2008target 2010
Solar
Solar
15.0 MWWithdrawn / abandoned Coos, NHISO-NE Oct 2018target 2020
Battery storage project 120, Whatcom County
Battery storage
15.0 MWWithdrawn / abandoned Whatcom, WAWest Aug 2021target 2024
Solar project AC1-146, Pittsylvania County
Solar
15.0 MWWithdrawn / abandoned Pittsylvania, VAPJM Oct 2016target 2018
Solar project X1-024, Salem County
Solar
15.0 MWWithdrawn / abandoned Salem, NJPJM Feb 2011target 2012
Solar + storage project AH1-469, Montour County
Solar + storage
15.0 MWWithdrawn / abandoned Montour, PAPJM Sep 2021target 2023
Solar project AF1-095, Clearfield County
Solar
15.0 MWWithdrawn / abandoned Clearfield, PAPJM Aug 2019target 2023
Solar project AG2-425, Cambria County
Solar
15.0 MWWithdrawn / abandoned Cambria, PAPJM Mar 2021target 2023
Independence Solar Farm
Solar
15.0 MWWithdrawn / abandoned Warren, NJPJM Jul 2020target 2027
Stewartsville Solar Farm
Solar
15.0 MWWithdrawn / abandoned Warren, NJPJM Oct 2010target 2014
Wind
Onshore wind
14.9 MWWithdrawn / abandoned Barnstable, MAISO-NE Dec 2010target 2012
Solar project AC1-115, Caroline County
Solar
14.9 MWWithdrawn / abandoned Caroline, VAPJM Oct 2016target 2018
Turning Point Solar
Solar
14.9 MWWithdrawn / abandoned Noble, OHPJM Oct 2010target 2019
Pratts Junc. Substation - NG WMA Group 3
Battery storage
14.9 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Lashaway Substation - NG WMA Group 3
Battery storage
14.9 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Solar project 51, Polk County
Solar
14.9 MWWithdrawn / abandoned Polk, FLSoutheast Jan 2019target 2020
Milton
Solar
14.9 MWWithdrawn / abandoned Sussex, DEPJM Aug 2011target 2018
Fuel Cell
Other
14.8 MWWithdrawn / abandoned Hartford, CTISO-NE Feb 2018target 2021
Glens Falls Hydro
Hydro · Erie Boulevard Hydropower, LP
14.8 MWWithdrawn / abandoned Washington, NYNYISO Jul 2015
Solar project AG2-654, Armstrong County
Solar · IMG Solar LLC
14.7 MWWithdrawn / abandoned Armstrong, PAPJM Jan 2025target 2022
Solar project J694, Iberia Parish County
Solar
14.7 MWWithdrawn / abandoned Iberia Parish, LAMISO Jul 2016target 2018
McAdoo repower
Onshore wind
14.7 MWWithdrawn / abandoned Dickens, TXERCOT Oct 2019
Gas project GI-0721, Williams County
Gas
14.5 MWWithdrawn / abandoned Williams, NDWest Nov 2007target 2009
Wellhead Renewables Fresno
Gas
14.5 MWWithdrawn / abandoned Fresno, CACAISO Oct 2009target 2014
BR Project 2
Solar + storage · NYSERDA
14.5 MWWithdrawn / abandoned Tompkins, NYNYISO Aug 2023
Solar project 421, Baker County
Solar · FPL
14.5 MWWithdrawn / abandoned Baker, FLSoutheast Mar 2021target 2025
Page 417 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)