Orient Point BESS

Orient Point BESS is a 15.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Suffolk County, New York, connecting to LIPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2021 (completed)
  2. Withdrawn / abandonedFeb 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1312
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
Saturn Energy Storage LLC
Connection point (POI)
The existing 23kV line near PSEG?s 23 kV Orient substation
Location
Suffolk County, New York
Technology
Battery: 15.0 MW
Total requested
15.0 MW
Queue status
Withdrawn
Entered queue
10 December 2021
Withdrawn
February 2022

Location

Marker shows the centre of Suffolk County; the queue data does not give exact sites.