United States βΊ Grid βΊ Interconnection queues βΊ Ohio
SOLAR Β· PJMTurning Point Solar
Turning Point Solar is a 15.0 MW solar request withdrawn in the PJM interconnection queue, in Noble County, Ohio, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2010 (completed)
- Withdrawn / abandonedJul 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- W3-112
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- S. Cumberland 69kV
- Location
- Noble County, Ohio
- Technology
- Solar: 15.0 MW
- Total requested
- 15.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Withdrawn
- Entered queue
- 29 October 2010
- Proposed online date
- April 2018
- Withdrawn
- July 2018
Location
Marker shows the centre of Noble County; the queue data does not give exact sites.
Other requests in Noble County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem