🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Jersey

SOLAR · PJM

Stewartsville Solar Farm

Stewartsville Solar Farm is a 15.0 MW solar request withdrawn in the PJM interconnection queue, in Warren County, New Jersey, connecting to JCPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2010 (completed)
  2. Withdrawn / abandonedSep 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
W3-095
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
JCPL
Connection point (POI)
Broadway-Stewartsville#2 34.5kV
Location
Warren County, New Jersey
Technology
Solar: 15.0 MW
Total requested
15.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Withdrawn
Entered queue
26 October 2010
Proposed online date
September 2014
Withdrawn
September 2014

Location

Marker shows the centre of Warren County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Warren County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem