🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in West (non-ISO utilities) — page 41

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,277949.5 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,277 requests · page 41 of 106
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project C2-47, Laramie County
Solar + storage
160 MWWithdrawn / abandoned Laramie, WYWest Apr 2022target 2025
Onshore wind project 460, Millard County
Onshore wind
160 MWWithdrawn / abandoned Millard, UTWest Jan 2013
Solar project 922, Klamath County
Solar
160 MWWithdrawn / abandoned Klamath, ORWest Aug 2017target 2019
Solar + storage project G0882, Lane County
Solar + storage
160 MWWithdrawn / abandoned Lane, ORWest Jun 2023target 2030
Solar + storage project 387, Yellowstone County
Solar + storage
160 MWWithdrawn / abandoned Yellowstone, MTWest Jul 2020target 2023
Solar + storage project CS25-12, Garfield County
Solar + storage
160 MWWithdrawn / abandoned Garfield, WAWest Apr 2025target 2029
Solar project 2019-G4
Solar
160 MWWithdrawn / abandoned West Mar 2019target 2022
Solar + storage project C1-18, Tooele County
Solar + storage
160 MWWithdrawn / abandoned Tooele, UTWest May 2021target 2025
Onshore wind project CLPT G13, Laramie County
Onshore wind
160 MWWithdrawn / abandoned Laramie, WYWest Aug 2017target 2019
Other project Q556, Navajo County
Other
160 MWWithdrawn / abandoned Navajo, AZWest May 2024target 2028
Battery storage project C3-136, Tooele County
Battery storage
160 MWWithdrawn / abandoned Tooele, UTWest May 2023target 2027
Onshore wind project 315, Power County
Onshore wind
160 MWWithdrawn / abandoned Power, IDWest Jan 2010target 2012
Solar project 1107, Albany County
Solar
160 MWWithdrawn / abandoned Albany, WYWest Jan 2019target 2022
Other project G0878, Lane County
Other
160 MWWithdrawn / abandoned Lane, ORWest Jun 2023target 2030
Solar + storage project 1073, Juab County
Solar + storage
160 MWWithdrawn / abandoned Juab, UTWest Oct 2018target 2021
Solar + storage project 1074, Utah County
Solar + storage
160 MWWithdrawn / abandoned Utah, UTWest Oct 2018target 2021
Desert Claim
Onshore wind · enXco Northwest
159 MWWithdrawn / abandoned Kittitas, WAWest Jun 2002target 2009
Onshore wind project GI-0923, Mccone County
Onshore wind
158 MWWithdrawn / abandoned Mccone, MTWest Aug 2009target 2012
Gas project 425, Sublette County
Gas
156 MWWithdrawn / abandoned Sublette, WYWest Jun 2012target 2016
Solar + storage project G0667, Yakima County
Solar + storage
156 MWWithdrawn / abandoned Yakima, WAWest Jan 2021target 2024
Battery storage project Q405, Yuma County
Battery storage
154 MWWithdrawn / abandoned Yuma, AZWest Sep 2021target 2025
Onshore wind project PIS022, Bonneville County
Onshore wind · PacifiCorp
153 MWWithdrawn / abandoned Bonneville, IDWest Jun 2022target 2026
Battery storage project Q96, Maricopa County
Battery storage
153 MWWithdrawn / abandoned Maricopa, AZWest Sep 2022target 2024
Onshore wind project 2004-G7
Onshore wind
153 MWWithdrawn / abandoned West Aug 2004target 2009
Onshore wind project G0339, Umatilla County
Onshore wind
152 MWWithdrawn / abandoned Umatilla, ORWest Jul 2008target 2013
Onshore wind project 2020-G1
Onshore wind
152 MWWithdrawn / abandoned West Nov 2019target 2022
Onshore wind project 225, Umatilla County
Onshore wind · Athena-Weston Wind Power Project, LLC
151 MWWithdrawn / abandoned Umatilla, ORWest May 2008
Onshore wind project 226, Umatilla County
Onshore wind · Athena-Weston Wind Power Project, LLC
151 MWWithdrawn / abandoned Umatilla, ORWest May 2008
Onshore wind project GI-2004-1, Morgan County
Onshore wind
150 MWWithdrawn / abandoned Morgan, COWest Jan 2004target 2006
Solar + storage project C3-102, Beaver County
Solar + storage
150 MWWithdrawn / abandoned Beaver, UTWest May 2023target 2026
Solar + storage project CS25-10, Spokane County
Solar + storage
150 MWWithdrawn / abandoned Spokane, WAWest Apr 2025target 2029
Solar project 19-09232, Larimer County
Solar
150 MWWithdrawn / abandoned Larimer, COWest Sep 2019target 2023
Battery storage project G0528, Clackamas County
Battery storage
150 MWWithdrawn / abandoned Clackamas, ORWest Feb 2016target 2017
Onshore wind project GI-2016-19, Lincoln County
Onshore wind
150 MWWithdrawn / abandoned Lincoln, COWest Sep 2016target 2019
Onshore wind project C3-033, Cowlitz County
Onshore wind
150 MWWithdrawn / abandoned Cowlitz, WAWest May 2023target 2027
Solar project GI-2009-10, Saguache County
Solar
150 MWWithdrawn / abandoned Saguache, COWest Dec 2009target 2013
Battery storage project C2-66, Weber County
Battery storage
150 MWWithdrawn / abandoned Weber, UTWest May 2022target 2024
Onshore wind project CLPT G25, Converse County
Onshore wind
150 MWWithdrawn / abandoned Converse, WYWest Apr 2023target 2026
Solar + storage project 22-107, Garfield County
Solar + storage
150 MWWithdrawn / abandoned Garfield, WAWest Jan 2022target 2024
Solar project IA-PNM-2017-02, Sandoval County
Solar
150 MWWithdrawn / abandoned Sandoval, NMWest Jan 2017target 2020
Solar + storage project C4-029, Caribou County
Solar + storage
150 MWWithdrawn / abandoned Caribou, IDWest May 2024target 2029
Solar + storage project PIS038, Cache County
Solar + storage
150 MWWithdrawn / abandoned Cache, UTWest May 2023target 2026
Onshore wind project 675, Bingham County
Onshore wind
150 MWWithdrawn / abandoned Bingham, IDWest Oct 2022
Solar + storage project C3-086, Klamath County
Solar + storage · PacifiCorp
150 MWWithdrawn / abandoned Klamath, ORWest May 2023target 2029
Onshore wind project 235, Union County
Onshore wind
150 MWWithdrawn / abandoned Union, ORWest Mar 2008target 2012
Solar project Q13, Kern County
Solar
150 MWWithdrawn / abandoned Kern, CAWest Jun 2010target 2016
Solar project GI-2017-25, Pueblo County
Solar
150 MWWithdrawn / abandoned Pueblo, COWest Aug 2017target 2019
Windy Ridge Wind Farm
Onshore wind · Winds Over Washington Energy Group
150 MWWithdrawn / abandoned Garfield, WAWest Oct 2001target 2004
Solar project 743, Bingham County
Solar
150 MWWithdrawn / abandoned Bingham, IDWest Oct 2023target 2026
Solar project Q28, San Bernardino County
Solar
150 MWWithdrawn / abandoned San Bernardino, CAWest May 2012target 2015
Page 41 of 106

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)