πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Idaho

ONSHORE WIND Β· WEST

Onshore wind project 315, Power County

Onshore wind project 315, Power County is a 160 MW onshore wind request withdrawn in the West interconnection queue, in Power County, Idaho, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2010 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
315
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Brady-Treasureton 230kV line
Location
Power County, Idaho
Technology
Wind: 160 MW
Total requested
160 MW
Service type
Network resource (NRIS)
Study phase
WITHDRAWN BY CUSTOMER
Queue status
Withdrawn
Entered queue
19 January 2010
Proposed online date
November 2012

Location

Marker shows the centre of Power County; the queue data does not give exact sites.

Power plants in Idaho Β· Transmission lines in Idaho

Other requests in Power County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem