Solar + storage project C4-029, Caribou County

Solar + storage project C4-029, Caribou County is a 150 MW solar + storage request withdrawn in the West interconnection queue, in Caribou County, Idaho, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2024 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
C4-029
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Fish Creek substation
Location
Caribou County, Idaho
Technology
Solar: 150 MW Β· Battery
Total requested
150 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
13 May 2024
Proposed online date
December 2029

Location

Marker shows the centre of Caribou County; the queue data does not give exact sites.

Power plants in Idaho Β· Transmission lines in Idaho

Other requests in Caribou County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem