United States › Grid › Interconnection queues › Texas

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Texas (2023 requests) — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown36979.0 GW
Active in queue79.0 GW369 requests
Agreement signed25.0 GW108 requests
Withdrawn11324.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

369 requests · page 4 of 8
ProjectCapacityStatusLocationRegionQueuedOnline
Marcus Energy Storage
Battery storage · Marcus Energy Storage, LLC
201 MWIn study Brazoria, TXERCOT Jun 2023target 2027
Copano Bay Energy Storage
Battery storage · Copano Bay Energy Storage, LLC
201 MWIn study Brazoria, TXERCOT Oct 2023target 2027
Timberline Solar
Solar + storage · Timberline Renewables, LLC
201 MWIn study Nacogdoches, TXERCOT Aug 2023target 2029
Felix West Solar
Solar + storage · Felix 1, LLC
201 MWAgreement signed Wilbarger, TXERCOT Jan 2023target 2028
Castle Corral BESS
Battery storage
201 MWPaused / redesign Mills, TXERCOT Jul 2023target 2026
Felix East Solar
Solar + storage · Felix 1, LLC
201 MWAgreement signed Wilbarger, TXERCOT Jan 2023target 2028
Cottontail Energy Center
Battery storage · Cottontail Energy Center, LLC
201 MWIn study Colorado, TXERCOT Oct 2023target 2027
Kahla Storage
Battery storage · BT Kahla Storage, LLC
201 MWIn study Leon, TXERCOT Aug 2023target 2028
Bell Creek BESS
Battery storage · BELL CREEK BESS, LLC
201 MWAgreement signed Brazoria, TXERCOT Jun 2023target 2027
Fike BESS
Battery storage · BRP Blue Topaz 9, LLC
201 MWIn study Hidalgo, TXERCOT May 2023target 2027
Pecos Storage Center
Wind + storage · Laurel Energy Center, LLC
201 MWAgreement signed Pecos, TXERCOT Sep 2023target 2027
Falcon Zapata Storage 138
Battery storage · Falcon BESS, LLC
201 MWIn study Zapata, TXERCOT May 2023target 2028
Augie BESS
Battery storage · BRP Blue Topaz 5, LLC
201 MWIn study Waller, TXERCOT Jan 2023target 2027
Blanquilla BESS
Battery storage · Blanquilla BESS LLC
201 MWAgreement signed Nueces, TXERCOT Feb 2023target 2027
Bobcat Cameron BESS
Battery storage · Bobcat BESS, LLC
201 MWIn study Cameron, TXERCOT Apr 2023target 2027
Longday Solar SLF
Solar + storage · Longday Solar
201 MWIn study Kinney, TXERCOT Jul 2023target 2027
Eagle Claw Energy Center
Battery storage · Eagle Claw Energy Center, LLC
201 MWAgreement signed Grimes, TXERCOT Oct 2023target 2027
Stinger Energy Storage
Battery storage · Stinger Energy Storage LLC
201 MWIn study Harris, TXERCOT Nov 2023target 2028
Anila Solar
Solar + storage · Alina Energy LLC
201 MWAgreement signed Wilson, TXERCOT Jan 2023target 2028
Beitel Energy Storage
Battery storage · Brazos Energy Storage, LLC
201 MWIn study Jack, TXERCOT Aug 2023target 2027
Red Top Solar I
Solar · Cat Red Top Solar, LLC
201 MWIn study Young, TXERCOT Jan 2023target 2028
Waterloo Solar 1
Solar + storage · Waterloo Solar, LLC
201 MWAgreement signed Bastrop, TXERCOT Apr 2023target 2027
JackGard BESS
Battery storage · Jackgard BESS
201 MWIn study Jack, TXERCOT Aug 2023target 2028
Vaughn Energy Storage
Battery storage · Vaughn Battery Storage, LLC
201 MWIn study Grimes, TXERCOT Aug 2023target 2027
SunShiner ESS
Battery storage · SunShiner ESS LLC
200 MWIn study Zavala, TXERCOT Sep 2023target 2027
Other project GEN-2023-059, Harrison County
Other
200 MWIn study Harrison, TXSPP Sep 2023target 2029
PSE Gongora Hill TX Storage
Battery storage · PureSky Development Inc
200 MWIn study Starr, TXERCOT Feb 2023target 2027
Battery storage project GEN-2023-SR8, Hansford County
Battery storage
200 MWAgreement signed Hansford, TXSPP Feb 2023target 2026
Monument Hill Solar
Solar · RWE Solar Development, LLC
200 MWIn study Fayette, TXERCOT Oct 2023target 2027
Cascabel Wind 2
Onshore wind · Vaquero Wind Energy, LLC
198 MWAgreement signed Zapata, TXERCOT Mar 2023target 2027
Cascabel Wind 1
Onshore wind · Vaquero Wind Energy, LLC
198 MWAgreement signed Zapata, TXERCOT Mar 2023target 2027
Corralitos Wind 1
Onshore wind · Vaquero Wind Energy, LLC
196 MWAgreement signed Zapata, TXERCOT Jan 2023target 2027
Corralitos Wind 2
Onshore wind · Vaquero Wind Energy, LLC
195 MWAgreement signed Zapata, TXERCOT Jan 2023target 2027
HarryoungBESS
Solar + storage · Gransolar Texas Four LLC
190 MWIn study Cameron, TXERCOT Oct 2023target 2028
Timmerman Power Plant Phase 2
Gas · Lower Colorado River Authority
188 MWAgreement signed Caldwell, TXERCOT Sep 2023target 2026
Serrano Storage
Battery storage · Maverick ESS, LLC
186 MWIn study Maverick, TXERCOT Sep 2023target 2026
Wetzel BESS
Battery storage · Brown ESS, LLC
186 MWIn study Brown, TXERCOT Mar 2023target 2026
Maldives Solar
Solar · Maldives Solar LLC
184 MWAgreement signed Scurry, TXERCOT Jul 2023target 2028
Brazos River BESS
Battery storage · Brazos River BESS LLC
180 MWAgreement signed Brazoria, TXERCOT Oct 2023target 2027
Alliance Solar
Solar
180 MWPaused / redesign Navarro, TXERCOT Jul 2023target 2028
Indigo solar 2
Solar + storage · Indigo Solar 2
180 MWIn study Fisher, TXERCOT Oct 2023target 2027
Willis Storage
Battery storage · BT Majewski Storage LLC
176 MWAgreement signed Rains, TXERCOT Mar 2023target 2027
McMurtre Storage
Battery storage · BT McMurtre Storage, LLC
176 MWIn study Hunt, TXERCOT Mar 2023target 2027
Brotherton Storage
Battery storage · BT Brotherton Storage, LLC
176 MWAgreement signed Anderson, TXERCOT Apr 2023target 2027
Yooperlite Storage
Battery storage · BT Yooperlite Storage, LLC
176 MWIn study Wise, TXERCOT Jun 2023target 2028
Hackberry Creek Solar
Solar · Hackberry Creek Solar LLC
176 MWAgreement signed Mitchell, TXERCOT Jul 2023target 2028
Sol Marina Energy Center
Solar + storage · Adapture Solar Development, LLC
175 MWAgreement signed Ellis, TXERCOT Oct 2023target 2027
Solar + storage project GEN-2023-193, Harrison County
Solar + storage
175 MWIn study Harrison, TXSPP Oct 2023target 2028
Cold Creek Storage 2
Solar + storage · Cold Creek Solar LLC
174 MWAgreement signed Schleicher, TXERCOT Dec 2023target 2028
Pethrus BESS
Battery storage · Pethrus BESS, LLC
174 MWIn study Wichita, TXERCOT Sep 2023target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)