Requests shown2,138571.6 GW
Active in queue179.2 GW464 requests
Agreement signed81.7 GW215 requests
Withdrawn2,138571.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,138 requests · page 4 of 43
ProjectCapacityStatusLocationRegionQueuedOnline
Etiwanda CCGT
Gas
698 MWWithdrawn / abandoned San Bernardino, CACAISO Oct 2006target 2013
City Of Vernon Renewable Project 1
Onshore wind
688 MWWithdrawn / abandoned Kern, CACAISO Jul 2009target 2013
Edison Drive Energy Storage
Battery storage
672 MWWithdrawn / abandoned Ventura, CACAISO Apr 2021target 2024
Sunstone
Solar + storage
672 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Huxley Solar
Solar + storage
671 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2021target 2027
Bryon Highway Power Bank
Gas
663 MWWithdrawn / abandoned CACAISO Apr 2023target 2031
Railway Power Bank
Battery storage
656 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
McFarland D
Solar + storage
651 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Oakley Generating Station
Gas
651 MWWithdrawn / abandoned Contra Costa, CACAISO Sep 2007target 2020
Ashanti Hybrid Solar
Solar + storage
650 MWWithdrawn / abandoned Riverside, CACAISO Apr 2021target 2024
Morro Bay Wave Energy Project
Other
650 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2015target 2020
Alta Q175 (Fka Alta 11)
Onshore wind
650 MWWithdrawn / abandoned Kern, CACAISO Feb 2007target 2017
Steel City Energy Storage
Battery storage
650 MWWithdrawn / abandoned Contra Costa, CACAISO Apr 2019target 2025
Antioch Generating Station
Gas
650 MWWithdrawn / abandoned Contra Costa, CACAISO Nov 2007target 2012
South Bay Replacement - Option 1
Gas
650 MWWithdrawn / abandoned San Diego, CACAISO Feb 2004target 2010
Ventus Renewable Energy Center
Other
643 MWWithdrawn / abandoned Riverside, CACAISO Apr 2019target 2023
Blythe III (Revised)
Gas
640 MWWithdrawn / abandoned Riverside, CACAISO Jun 2007target 2015
Pastoria Creek Power Bank
Battery storage
636 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Mojave Solar Park 1
Solar
635 MWWithdrawn / abandoned San Bernardino, CACAISO May 2006target 2010
Bluff Trail Storage
Battery storage
632 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2020target 2027
Salton Solar
Solar + storage
632 MWWithdrawn / abandoned Imperial, CACAISO Apr 2019target 2023
CPV California Ix
Gas
630 MWWithdrawn / abandoned Solano, CACAISO Nov 2007target 2013
CPV California Viii
Gas
630 MWWithdrawn / abandoned San Joaquin, CACAISO Jun 2007target 2011
CPV California Vii
Gas
630 MWWithdrawn / abandoned Contra Costa, CACAISO Jun 2007target 2011
CPV California VI
Gas
630 MWWithdrawn / abandoned Alameda, CACAISO Jun 2007target 2011
Seaglass Offshore Wind
Offshore wind
629 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2021target 2032
Pecho Energy Storage
Other
628 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2020target 2031
Lion Rock Offshore Wind
Offshore wind
627 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2026
Belmont
Solar + storage
627 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Birch Street Generation Facility (Fka Birch Street- Simple Cycle)
Gas
625 MWWithdrawn / abandoned Orange, CACAISO Apr 2014target 2018
Grand Ave Generation Facility (Fka Grand Ave Simple Cycle)
Gas
625 MWWithdrawn / abandoned Orange, CACAISO Apr 2014target 2018
Natura
Other
623 MWWithdrawn / abandoned Riverside, CACAISO Apr 2021target 2025
Ventoso
Other
623 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2020target 2027
Date Palm
Battery storage
621 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2023target 2031
Avenal Energy Project
Gas
620 MWWithdrawn / abandoned Kings, CACAISO May 2001target 2009
Rainbow Energy Facility
Gas
620 MWWithdrawn / abandoned San Diego, CACAISO Jun 2007target 2012
Astra
Other
620 MWWithdrawn / abandoned Riverside, CACAISO Apr 2020target 2024
Fortuna
Other
620 MWWithdrawn / abandoned Riverside, CACAISO Apr 2020target 2024
Valorem
Other
619 MWWithdrawn / abandoned Kern, CACAISO Apr 2020target 2024
Fort Tejon Solar
Solar + storage
617 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2019target 2026
Fortis
Other
616 MWWithdrawn / abandoned Solano, CACAISO Apr 2020target 2028
Charger Storage
Battery storage
616 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2025
Blue Oak Storage
Battery storage
616 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2021target 2025
Resonate
Solar + storage
615 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2021target 2024
Angel Energy Center
Battery storage
615 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Porta
Other
615 MWWithdrawn / abandoned Riverside, CACAISO Apr 2020target 2029
Waller Solar Farm
Solar + storage
615 MWWithdrawn / abandoned Kern, CACAISO May 2016target 2023
Carson Hydrogen Power Project (CHPP)
Gas
614 MWWithdrawn / abandoned Los Angeles, CACAISO Feb 2006target 2011
Osito Energy
Solar + storage
613 MWWithdrawn / abandoned Placer, CACAISO Apr 2021target 2024
Voltron
Solar + storage
612 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2021target 2024
Page 4 of 43

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)