United States › Grid › Interconnection queues › California

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in California — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24897.3 GW
Active in queue179.2 GW464 requests
Agreement signed81.7 GW215 requests
Withdrawn2,138571.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

248 requests · page 4 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project 16, Sacramento County
Battery storage
204 MWIn study Sacramento, CAWest Jan 2022target 2027
Phaenon
Solar + storage
204 MWIn study Kern, CACAISO Apr 2021target 2029
Puma Storage
Battery storage
204 MWIn study Madera, CACAISO Apr 2021target 2030
Puff Hybrid Solar
Solar + storage
204 MWIn study Kern, CACAISO Apr 2020target 2030
Brundage Energy Storage
Battery storage
202 MWIn study Los Angeles, CACAISO Apr 2023target 2029
Everest Energy Storage
Battery storage
202 MWIn study Kern, CACAISO Apr 2021target 2030
Battery storage project Q81, Los Angeles County
Battery storage
200 MWIn study Los Angeles, CAWest May 2021target 2024
Tendril
Solar + storage
200 MWIn study Kern, CACAISO Apr 2023target 2031
Merlin Storage
Battery storage
200 MWIn study Los Angeles, CACAISO Apr 2021target 2032
Battery storage project SC1Q32, Sacramento County
Battery storage
200 MWIn study Sacramento, CAWest Jul 2025target 2031
Battery storage project 11, Sacramento County
Battery storage
200 MWIn study Sacramento, CAWest Apr 2021target 2026
Conduit Energy Storage 2
Battery storage
199 MWIn study San Bernardino, CACAISO Apr 2023target 2031
Buttercup Hybrid Solar
Solar + storage
197 MWIn study Merced, CACAISO Apr 2021target 2032
Lycan Solar 2
Solar
192 MWIn study Riverside, CACAISO Apr 2023target 2028
Solar + storage project GI-2021-149, Imperial County
Solar + storage
175 MWIn study Imperial, CAWest Nov 2021target 2024
Solar + storage project Q30, Kern County
Solar + storage
170 MWPaused / redesign Kern, CAWest Jun 2012target 2014
Conaway Hybrid Power Plant
Solar + storage
170 MWIn study Yolo, CACAISO Apr 2020target 2023
Battery storage project 22, Sacramento County
Battery storage
160 MWIn study Sacramento, CAWest Jul 2022target 2027
Solar + storage project 2019-G42, San Bernardino County
Solar + storage
160 MWIn study San Bernardino, CAWest Jun 2019target 2021
Geothermal project GI-2023-174, Imperial County
Geothermal
157 MWIn study Imperial, CAWest Apr 2023target 2029
Geothermal project GI-2023-176, Imperial County
Geothermal
157 MWIn study Imperial, CAWest Apr 2023target 2029
Hacienda
Solar
157 MWIn study San Bernardino, CACAISO Apr 2023target 2030
Solar + storage project 30, Sacramento County
Solar + storage
156 MWIn study Sacramento, CAWest Dec 2022target 2029
Argenta
Solar
156 MWIn study San Bernardino, CACAISO Apr 2023target 2031
Zinfandel Storage Center
Battery storage
154 MWIn study San Joaquin, CACAISO Apr 2023target 2030
Bobor Storage
Battery storage
152 MWIn study Tulare, CACAISO Apr 2021target 2030
Flores Storage
Battery storage
152 MWIn study Madera, CACAISO Apr 2021target 2031
Solar + storage project GI-2023-175, Imperial County
Solar + storage
150 MWIn study Imperial, CAWest Apr 2023target 2028
Battery storage project 27, Sacramento County
Battery storage
150 MWIn study Sacramento, CAWest Oct 2022target 2027
Battery storage project T2-072, Siskiyou County
Battery storage
150 MWIn study Siskiyou, CAWest Sep 2025target 2027
Solar + storage project GI-2023-173, Imperial County
Solar + storage
150 MWIn study Imperial, CAWest Apr 2023target 2028
Solar project GI-2023-170, Imperial County
Solar
150 MWIn study Imperial, CAWest Apr 2023target 2026
Reflex
Solar
129 MWIn study Riverside, CACAISO Apr 2023target 2029
Holly Oaks
Battery storage
128 MWIn study Calaveras, CACAISO Apr 2023target 2028
Battery storage project GI-2021-145, Riverside County
Battery storage
125 MWIn study Riverside, CAWest Aug 2021target 2027
Solar + storage project GI-2022-163, Riverside County
Solar + storage
125 MWIn study Riverside, CAWest Sep 2022target 2025
Solar + storage project 2024-G2, Shasta County
Solar + storage
125 MWIn study Shasta, CAWest Nov 2024target 2028
El Rey Power Bank
Battery storage
124 MWIn study Monterey, CACAISO Apr 2021target 2029
Bonita Bateria 2
Battery storage
123 MWIn study Orange, CACAISO Apr 2023target 2029
Wildhorse Energy Center
Battery storage
122 MWIn study Sonoma, CACAISO Apr 2021target 2030
High Winds Storage
Battery storage
121 MWIn study Solano, CACAISO Apr 2021target 2031
Sienna Solar 2
Solar + storage
112 MWIn study San Bernardino, CACAISO Apr 2021target 2029
Toland Renewable Energy Park
Onshore wind
108 MWIn study Solano, CACAISO Apr 2023target 2029
Voyager Energy Storage
Battery storage
105 MWIn study Kern, CACAISO Apr 2023target 2027
Ulua
Battery storage
105 MWIn study Los Angeles, CACAISO Apr 2023target 2029
Tioga Pass
Battery storage
103 MWIn study San Joaquin, CACAISO Apr 2023target 2028
Bonita Bateria
Battery storage
103 MWIn study Orange, CACAISO Apr 2023target 2029
Cassia
Battery storage
102 MWIn study San Joaquin, CACAISO Apr 2023target 2031
Arges BESS
Battery storage
102 MWIn study Solano, CACAISO Apr 2021target 2029
Pajaro Valley Storage
Battery storage
102 MWIn study San Diego, CACAISO Apr 2021target 2030

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)