Battery storage project Q81, Los Angeles County

Battery storage project Q81, Los Angeles County is a 200 MW battery storage request in interconnection study in the West interconnection queue, in Los Angeles County, California, connecting to Los Angeles Department of Water and Power.

Queue statusIn planning
  1. PlanningQueued May 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q81
Grid region
West (non-ISO utilities)
Utility / transmission owner
Los Angeles Department of Water and Power
Connection point (POI)
Northridge 230 kV Substation
Location
Los Angeles County, California
Technology
Battery: 200 MW
Total requested
200 MW
Study phase
Application received
Queue status
Active
Entered queue
11 May 2021
Proposed online date
August 2024

Location

Marker shows the centre of Los Angeles County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Los Angeles County