United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in West (non-ISO utilities) — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,496455.6 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,496 requests · page 4 of 30
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project G0812, Lane County
Battery storage
600 MWIn study Lane, ORWest Sep 2022target 2030
Other project G0806, Douglas County
Other
600 MWIn study Douglas, ORWest Sep 2022target 2028
Solar + storage project Company 200, Clark County
Solar + storage
600 MWPaused / redesign Clark, NVWest Sep 2021target 2029
Gas project 25-00428, Lincoln County
Gas
600 MWIn study Lincoln, NVWest Jul 2025target 2028
Geothermal project 25-00412, Humboldt County
Geothermal
600 MWIn study Humboldt, NVWest Jul 2025target 2032
Solar + storage project Company NU, White Pine County
Solar + storage
600 MWPaused / redesign White Pine, NVWest Sep 2022target 2029
Gas project T2-034, Sweetwater County
Gas · PacifiCorp
600 MWIn study Sweetwater, WYWest Sep 2025target 2030
Solar + storage project Company 254, Nye County
Solar + storage
600 MWIn study Nye, NVWest Sep 2023target 2026
Solar + storage project Company NX, White Pine County
Solar + storage
600 MWPaused / redesign White Pine, NVWest Sep 2022target 2025
Solar + storage project Company OT, Lander County
Solar + storage
600 MWPaused / redesign Lander, NVWest Jan 2023target 2027
Wind + storage project G1007, Lewis County
Wind + storage
600 MWIn study Lewis, WAWest Nov 2023target 2030
Solar + storage project 25-00395, Washoe County
Solar + storage
600 MWIn study Washoe, NVWest Jul 2025target 2028
Solar + storage project Company NW, White Pine County
Solar + storage
600 MWPaused / redesign White Pine, NVWest Sep 2022target 2025
Gas project 37316, Laramie County
Gas
600 MWIn study Laramie, WYWest Jul 2025target 2027
Other project G0854, Umatilla County
Other
600 MWIn study Umatilla, ORWest Apr 2023target 2025
Solar + storage project Company 255, Nye County
Solar + storage
600 MWIn study Nye, NVWest Sep 2023target 2027
Solar + storage project Q2415, Maricopa County
Solar + storage
600 MWIn study Maricopa, AZWest Feb 2024target 2028
Solar + storage project 90, Pima County
Solar + storage
600 MWIn study Pima, AZWest Jan 2021target 2025
Gas project T2-033, Sweetwater County
Gas · PacifiCorp
600 MWIn study Sweetwater, WYWest Sep 2025target 2030
Solar + storage project Company NQ, White Pine County
Solar + storage
600 MWPaused / redesign White Pine, NVWest Aug 2022target 2025
Other project Q561, Maricopa County
Other
600 MWIn study Maricopa, AZWest May 2024target 2029
Other project G0811, Lane County
Other
600 MWIn study Lane, ORWest Sep 2022target 2030
Solar + storage project Company NV, Humboldt County
Solar + storage
600 MWPaused / redesign Humboldt, NVWest Sep 2022target 2030
Onshore wind project G0953, Lincoln County
Onshore wind
600 MWIn study Lincoln, WAWest Oct 2023target 2026
Onshore wind project 361, Wheatland County
Onshore wind
600 MWIn study Wheatland, MTWest Mar 2019target 2021
Solar + storage project 25-00416, Humboldt County
Solar + storage
600 MWIn study Humboldt, NVWest Jul 2025target 2028
Other project G0768, Gilliam County
Other
600 MWIn study Gilliam, ORWest Aug 2022target 2027
Wind + storage project Company LV, White Pine County
Wind + storage
600 MWPaused / redesign White Pine, NVWest Sep 2021target 2025
Solar + storage project Q49, Millard County
Solar + storage · Intermountain Power Agency
600 MWIn study Millard, UTWest Aug 2015target 2020
Solar + storage project Company NC, Washoe County
Solar + storage
600 MWPaused / redesign Washoe, NVWest Mar 2022target 2030
Solar + storage project G0840, Douglas County
Solar + storage
600 MWIn study Douglas, WAWest Feb 2023target 2027
Geothermal project 25-00406, Churchill County
Geothermal
600 MWIn study Churchill, NVWest Jul 2025target 2029
Solar + storage project G0841, Lake County
Solar + storage
600 MWIn study Lake, ORWest Feb 2023target 2028
Gas project 25-00422, Lincoln County
Gas
600 MWIn study Lincoln, NVWest Jul 2025target 2028
Solar + storage project Company 224, Clark County
Solar + storage
600 MWPaused / redesign Clark, NVWest Aug 2022target 2030
Geothermal project 25-00409, Churchill County
Geothermal
600 MWIn study Churchill, NVWest Jul 2025target 2033
Battery storage project G0808, Douglas County
Battery storage
600 MWIn study Douglas, ORWest Sep 2022target 2030
Solar project G0673, Crook County
Solar
600 MWIn study Crook, ORWest Mar 2021target 2028
Battery storage project G0643, Crook County
Battery storage
600 MWIn study Crook, ORWest Feb 2020target 2024
Gas project T2-017, Converse County
Gas · PacifiCorp
600 MWIn study Converse, WYWest Aug 2025target 2029
Solar + storage project Q80, Kern County
Solar + storage
590 MWIn study Kern, CAWest Apr 2021target 2024
Solar + storage project Q387, Navajo County
Solar + storage
588 MWIn study Navajo, AZWest Mar 2021target 2025
Solar + storage project Q53, Millard County
Solar + storage · Intermountain Power Agency
570 MWIn study Millard, UTWest Jul 2016target 2019
Gas project 25-00430, Storey County
Gas
570 MWIn study Storey, NVWest Jul 2025target 2030
Solar + storage project Q2406, Maricopa County
Solar + storage
565 MWIn study Maricopa, AZWest Feb 2024target 2029
Other project 110, Garfield County
Other
560 MWIn study Garfield, WAWest Jan 2021target 2025
Solar + storage project G0826, Klamath County
Solar + storage
560 MWIn study Klamath, ORWest Nov 2022target 2027
Onshore wind project 5RSC-2024-29, Yuma County
Onshore wind
554 MWIn study Yuma, COWest Jan 2024target 2027
Solar + storage project Company LW, Mineral County
Solar + storage
550 MWPaused / redesign Mineral, NVWest Sep 2021target 2029
Battery storage project Company MV, White Pine County
Battery storage
550 MWPaused / redesign White Pine, NVWest Mar 2022target 2030
Page 4 of 30

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)