United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Completed queue projects in West (non-ISO utilities) — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown96364.7 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

963 requests · page 4 of 20
ProjectCapacityStatusLocationRegionQueuedOnline
Tuolumne Wind (Windy Point 1)
Onshore wind · Windy Point Partners, LLC
125 MWOperating Klickitat, WAWest Jul 2005target 2007
Gas project GI-1406, Williams County
Gas · Basin Electric
125 MWOperating Williams, NDWest Jun 2014target 2016
Solar project Q09, Maricopa County
Solar
125 MWOperating Maricopa, AZWest Jan 20092016
Gas project GI-1206, Mckenzie County
Gas · Basin Electric
125 MWOperating Mckenzie, NDWest Apr 2012target 2016
Solar project ANPP HVS-Q09
Solar
125 MWOperating West Jan 2009target 2016
Onshore wind project 29-B, Bonneville County
Onshore wind · Wolverine Creek Goshen Interconnection, LLC
125 MWOperating Bonneville, IDWest Sep 2003target 2010
Solar project 737, Washington County
Solar · Cove Mountain Solar 2, LLC
122 MWOperating Washington, UTWest Apr 2016target 2020
Onshore wind project 341, Bonneville County
Onshore wind · Meadow Creek Project Company, LLC
120 MWOperating Bonneville, IDWest Jun 2010target 2012
Gas project CLPT-G2, Laramie County
Gas · Cheyenne Light Fuel & Power
120 MWOperating Laramie, WYWest Jun 2011target 2014
Gas project GI-0708, Roosevelt County
Gas · BEPC
120 MWOperating Roosevelt, MTWest May 2007target 2010
Sky Ranch Solar / Sky Ranch Energy Storage
Solar
120 MWOperating Sandoval, NMWest Jan 2017target 2021
Gas project 11, Salt Lake County
Gas · PacifiCorp Commercial & Trading
120 MWOperating Salt Lake, UTWest Jul 2001target 2002
Hydro project 795, Power County
Hydro · Idaho Power Company - Power Supply
118 MWOperating Power, IDWest Jul 2025
Solar + storage project ANPP HVS-Q24
Solar + storage
115 MWOperating West Dec 2017target 2024
Solar + storage project Q24, Maricopa County
Solar + storage
115 MWOperating Maricopa, AZWest Dec 2017target 2024
Onshore wind project 203, Carbon County
Onshore wind · PacifiCorp Commercial & Trading
111 MWOperating Carbon, WYWest Feb 2008target 2010
Gas project GI-0316, Brown County
Gas · BEPC
110 MWOperating Brown, SDWest Aug 2003target 2006
Onshore wind project GI-0926, Morton County
Onshore wind · Sunflower Wind Proj.
110 MWOperating Morton, NDWest Oct 2009target 2016
Gas project 8, Lincoln County
Gas · Exxon Mobil Production Company
110 MWOperating Lincoln, WYWest Mar 2001target 2004
Coal project 5, Big Horn County
Coal
109 MWOperating Big Horn, MTWest Apr 20012006
Kittitas Valley Wind
Onshore wind · Sagebrush Power Partners, LLC
108 MWOperating Kittitas, WAWest Sep 2001target 2009
Gas project GI-0608, Brown County
Gas · BEPC
106 MWOperating Brown, SDWest Jul 2006target 2008
Duran Mesa
Onshore wind
105 MWOperating Torrence, NMWest Aug 2020target 2021
Onshore wind project TI-17-0224, Kit Carson County
Onshore wind
104 MWOperating Kit Carson, COWest Feb 20172020
Red Mesa Wind
Onshore wind
102 MWOperating Mckinley, NMWest
Onshore wind project 117, Twin Falls County
Onshore wind
102 MWOperating Twin Falls, IDWest Jan 20052010
Onshore wind project Q113, Coconino County
Onshore wind
101 MWOperating Coconino, AZWest Mar 2010target 2011
Solar project Company GV, Lander County
Solar
101 MWOperating Lander, NVWest Sep 2015target 2016
Onshore wind project 120, Union County
Onshore wind
101 MWOperating Union, ORWest Jan 2005target 2007
Solar project Q07c
Solar
100 MWOperating West Jun 20172022
White Creek
Onshore wind · Harvest Wind Project
100 MWOperating Klickitat, ORWest Apr 2002target 2009
Onshore wind project 78, Glacier County
Onshore wind
100 MWOperating Glacier, MTWest Dec 20072008
Solar project Q07, Pinal County
Solar
100 MWOperating Pinal, AZWest Jun 2017target 2022
Solar project Company 114, Clark County
Solar
100 MWOperating Clark, NVWest Sep 2013target 2016
Onshore wind project 87, Glacier County
Onshore wind
100 MWOperating Glacier, MTWest Apr 20082008
Solar project 777, Emery County
Solar · Hornshadow Solar, LLC
100 MWOperating Emery, UTWest Jul 2016target 2025
Gas project BHCT-G5, Pueblo County
Gas · Black Hills Electric Generation LLC
100 MWOperating Pueblo, COWest Apr 2009target 2011
Solar project Q44b
Solar
100 MWOperating West Apr 20182020
Onshore wind project 785, Natrona County
Onshore wind · Anticline Wind, LLC
100 MWOperating Natrona, WYWest Aug 2016target 2024
Gas project BHCT-G4, Pueblo County
Gas · Black Hills Electric Generation LLC
100 MWOperating Pueblo, COWest Apr 2009target 2011
Gas project Q17, Yuma County
Gas
100 MWOperating Yuma, AZWest Sep 2005target 2008
Solar project Q07b
Solar
100 MWOperating West Jun 20172022
EXUS NM Data Center III
Solar
100 MWOperating Sandoval, NMWest Jan 2017target 2022
Onshore wind project 17‚Äê07183
Onshore wind
100 MWOperating West target 2020
Solar project TI-18-0809, Las Animas County
Solar
100 MWOperating Las Animas, COWest Aug 20182024
Solar project PV-PC-Q07
Solar
100 MWOperating West Jun 2017target 2022
Onshore wind project 17-07183, Larimer County
Onshore wind
100 MWOperating Larimer, COWest Jul 2017target 2020
Solar + storage project Company KK, Eureka County
Solar + storage
100 MWOperating Eureka, NVWest Feb 2020target 2023
Onshore wind project 73, Glacier County
Onshore wind
100 MWOperating Glacier, MTWest Jul 20072008
Solar project Company 129, Clark County
Solar
100 MWOperating Clark, NVWest Sep 2013target 2016
Page 4 of 20

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)