United States βΊ Grid βΊ Interconnection queues
SOLAR Β· WESTSolar project Q44b
Solar project Q44b is a 100 MW solar request built and operating in the West interconnection queue.
Request details
- Queue ID
- Q44b
- Grid region
- West (non-ISO utilities)
- Connection point (POI)
- Vah-Ki 230 kV
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Study phase
- In-Service
- Queue status
- Operational
- Entered queue
- 26 April 2018
- Proposed online date
- December 2020
- Came online
- December 2020
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem