Onshore wind project 29-B, Bonneville County

Onshore wind project 29-B, Bonneville County is a 125 MW onshore wind request built and operating in the West interconnection queue, in Bonneville County, Idaho, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Sep 2003 (completed)
  2. ConsentedOct 2006 (completed)
  3. Construction (completed)
  4. OperatingTarget Oct 2010 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
29-B
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Wolverine Creek Goshen Interconnection, LLC
Connection point (POI)
Goshen substation (Idaho)
Location
Bonneville County, Idaho
Technology
Wind: 125 MW
Total requested
125 MW
Service type
Energy only (ERIS)
Study phase
IA signed 10/11/06, Revised IA w/ Q0243 signed 12/30/09
Queue status
Operational
Entered queue
18 September 2003
Agreement signed
11 October 2006
Proposed online date
October 2010

Location

Marker shows the centre of Bonneville County; the queue data does not give exact sites.