United States › Grid › Interconnection queues › Idaho
ONSHORE WIND · WESTOnshore wind project C2-91, Bonneville County
Onshore wind project C2-91, Bonneville County is a 153 MW onshore wind request in interconnection study in the West interconnection queue, in Bonneville County, Idaho, connecting to PacifiCorp.
Queue statusIn planning
- PlanningQueued May 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- C2-91
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Developer
- PacifiCorp
- Connection point (POI)
- Bonneville-Goshen transmission line
- Location
- Bonneville County, Idaho
- Technology
- Wind: 153 MW
- Total requested
- 153 MW
- Service type
- Energy only (ERIS)
- Study phase
- Facility Study
- Queue status
- Active
- Entered queue
- 12 May 2022
- Proposed online date
- December 2026
Location
Marker shows the centre of Bonneville County; the queue data does not give exact sites.
Other requests in Bonneville County
- Onshore wind project 29-B, Bonneville CountyOnshore wind · 125 MW · built
- Onshore wind project 341, Bonneville CountyOnshore wind · 120 MW · built
- Onshore wind project 29-A, Bonneville CountyOnshore wind · 64.5 MW · built
- Horse Butte WindOnshore wind · 57.6 MW · built
- Onshore wind project 563, Bonneville CountyOnshore wind · 950 MW · withdrawn
- Solar + storage project C2-73, Bonneville CountySolar + storage · 350 MW · withdrawn
- Onshore wind project C1-49, Bonneville CountyOnshore wind · 308 MW · withdrawn
- Solar + storage project G0967, Bonneville CountySolar + storage · 300 MW · withdrawn
- Onshore wind project 398-B, Bonneville CountyOnshore wind · 288 MW · withdrawn
- Solar project C4-090, Bonneville CountySolar · 199 MW · withdrawn
- Solar project C4-091, Bonneville CountySolar · 199 MW · withdrawn
- Onshore wind project 398-A, Bonneville CountyOnshore wind · 192 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem