ONSHORE WIND · WEST

Onshore wind project 120, Union County

Onshore wind project 120, Union County is a 101 MW onshore wind request built and operating in the West interconnection queue, in Union County, Oregon, connecting to Idaho Power Company.

Queue statusOperating
  1. PlanningQueued Jan 2005 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2007 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
120
Grid region
West (non-ISO utilities)
Utility / transmission owner
Idaho Power Company
Connection point (POI)
230kV
Location
Union County, Oregon
Technology
Wind: 101 MW
Total requested
101 MW
Service type
Network resource (NRIS)
Study phase
FeSR SISR FSR LGIA
Queue status
Operational
Entered queue
31 January 2005
Proposed online date
December 2007

Location

Marker shows the centre of Union County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Union County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem