Solar + storage project Q24, Maricopa County

Solar + storage project Q24, Maricopa County is a 115 MW solar + storage request built and operating in the West interconnection queue, in Maricopa County, Arizona, connecting to Salt River Project.

Queue statusOperating
  1. PlanningQueued Dec 2017 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Feb 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Q24
Grid region
West (non-ISO utilities)
Utility / transmission owner
Salt River Project
Connection point (POI)
Hassayampa 500 kV
Location
Maricopa County, Arizona
Technology
Solar: 115 MW · Battery
Total requested
115 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
27 December 2017
Proposed online date
February 2024

Location

Marker shows the centre of Maricopa County; the queue data does not give exact sites.

Power plants in Arizona · Transmission lines in Arizona

Other requests in Maricopa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem