SOLAR · WEST

Solar project Company 114, Clark County

Solar project Company 114, Clark County is a 100 MW solar request built and operating in the West interconnection queue, in Clark County, Nevada, connecting to NV Energy.

Queue statusOperating
  1. PlanningQueued Sep 2013 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Sep 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Company 114
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Clark County, Nevada
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
19 September 2013
Proposed online date
September 2016

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Clark County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem