OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 394

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 394 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Sabertooth Solar
Solar · Sabertooth Solar, LLC
20.0 MWWithdrawn / abandoned Cortland, NYNYISO Feb 2017
Solar project 86, Lincoln County
Solar
20.0 MWWithdrawn / abandoned Lincoln, WAWest May 2019target 2022
Geothermal project C4-002, Millard County
Geothermal
20.0 MWWithdrawn / abandoned Millard, UTWest Apr 2024
Solar + storage project 1231, Sweetwater County
Solar + storage
20.0 MWWithdrawn / abandoned Sweetwater, WYWest May 2020target 2023
Chestertown BESS
Battery storage · Saturn Energy Storage LLC
20.0 MWWithdrawn / abandoned Warren, NYNYISO Oct 2020
Patriot Solar B
Solar
20.0 MWWithdrawn / abandoned Fresno, CACAISO Mar 2011target 2018
Solar project Q75, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Oct 2009target 2010
Solar project W2-097, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, PAPJM Jul 2010target 2012
Parnell Solar
Solar · Parnell Solar, LLC
20.0 MWWithdrawn / abandoned Martin, NCPJM Sep 2020target 2023
Solar project AG2-337, Henry County
Solar · Reserve Energy Exploration Company
20.0 MWWithdrawn / abandoned Henry, OHPJM Mar 2021target 2023
Solar project W3-072, Franklin County
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Sep 2010target 2012
Double Lock Solar
Solar · Double Lock Solar, LLC
20.0 MWWithdrawn / abandoned Herkimer, NYNYISO Jul 2016
Riverhead - Phase 1
Solar · East Hampton Solar Farm 2, LLC
20.0 MWWithdrawn / abandoned Suffolk, NYNYISO Apr 2014
Solar project Q58, Pinal County
Solar
20.0 MWWithdrawn / abandoned Pinal, AZWest Apr 2019target 2022
Solar project AF2-334, Montour County
Solar
20.0 MWWithdrawn / abandoned Montour, PAPJM Mar 2020target 2023
Battery storage project AG2-229, Floyd County
Battery storage
20.0 MWWithdrawn / abandoned Floyd, VAPJM Mar 2021target 2024
Culpeper North
Solar
20.0 MWWithdrawn / abandoned Culpeper, VAPJM Mar 2017target 2021
Solar project AF1-284, Garrett County
Solar
20.0 MWWithdrawn / abandoned Garrett, MDPJM Sep 2019target 2021
Solar project W1-008, Accomack County
Solar
20.0 MWWithdrawn / abandoned Accomack, VAPJM Feb 2010target 2016
Battery storage project GEN-2015-044, Caddo County
Battery storage
20.0 MWWithdrawn / abandoned Caddo, OKSPP Oct 2015target 2017
Battery storage project AH1-739, Dorchester County
Battery storage · Richfield Solar Energy LLC
20.0 MWWithdrawn / abandoned Dorchester, MDPJM target 2028
Solar project IC-301, Tattnall County
Solar
20.0 MWWithdrawn / abandoned Tattnall, GASoutheast Jun 2013
Solar project AB2-182, Cecil County
Solar
20.0 MWWithdrawn / abandoned Cecil, MDPJM Apr 2016target 2017
Goldeneye Energy Storage Center
Battery storage
20.0 MWWithdrawn / abandoned Contra Costa, CACAISO Apr 2015target 2021
Solar project Y2-059, Somerset County
Solar
20.0 MWWithdrawn / abandoned Somerset, MDPJM Aug 2012target 2015
Port Jeff 2-Terryville Energy Storage
Battery storage · Setauket Energy Storage, LLC
20.0 MWWithdrawn / abandoned Suffolk, NYNYISO Apr 2019
Solar + storage project Company IP, Lyon County
Solar + storage
20.0 MWWithdrawn / abandoned Lyon, NVWest Apr 2018target 2021
Onshore wind project GI-1213, Valley County
Onshore wind
20.0 MWWithdrawn / abandoned Valley, MTWest Sep 2012target 2013
Solar project AH1-281, Nelson County
Solar · Soltage KY DevCo, LLC
20.0 MWWithdrawn / abandoned Nelson, KYPJM Mar 2025target 2024
ASD Warner PA2 Solar LLC
Solar · ASD Warner PA2 Solar LLC
20.0 MWWithdrawn / abandoned Tioga, PAPJM Aug 2021target 2023
Solar project Q93, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Jan 2010target 2012
Solar project IC-477, Dooly County
Solar
20.0 MWWithdrawn / abandoned Dooly, GASoutheast Aug 2016
Solar project J210, Butler County
Solar
20.0 MWWithdrawn / abandoned Butler, OHMISO Apr 2011target 2013
Solar project V2-018, Cape May County
Solar
20.0 MWWithdrawn / abandoned Cape May, NJPJM Jun 2009target 2010
Onshore wind project G0445, Cassia County
Onshore wind
20.0 MWWithdrawn / abandoned Cassia, IDWest Dec 2010target 2011
Solar project V3-061, Northampton County
Solar
20.0 MWWithdrawn / abandoned Northampton, VAPJM Oct 2009target 2011
Solar project AG1-395, Clearfield County
Solar
20.0 MWWithdrawn / abandoned Clearfield, PAPJM Sep 2020target 2022
Bethpage Battery Energy Storage System
Battery storage · Calpine Mid Atlantic Development, LLC
20.0 MWWithdrawn / abandoned Nassau, NYNYISO Dec 2019
wind
Onshore wind
20.0 MWWithdrawn / abandoned Franklin, VTISO-NE Jul 2017target 2020
Onshore wind project G0246, Cassia County
Onshore wind
20.0 MWWithdrawn / abandoned Cassia, IDWest Nov 2006target 2007
Solar project AG2-410, Southampton County
Solar
20.0 MWWithdrawn / abandoned Southampton, VAPJM Mar 2021target 2023
187 Finchville Turnpike, Mount Hope
Battery storage · 212 Solar Development, LLC
20.0 MWWithdrawn / abandoned Orange, NYNYISO Mar 2020
Bradley Ridge Solar
Solar
20.0 MWWithdrawn / abandoned Chesterfield, VAPJM Mar 2019target 2025
Gas project AH1-708, Adams County
Gas · Hunterstown Generation, LLC
20.0 MWWithdrawn / abandoned Adams, PAPJM target 2025
Monterey Solar Farm (Fka Bfo PV -09)
Solar
20.0 MWWithdrawn / abandoned Monterey, CACAISO Aug 2010target 2012
Onshore wind project GI-0913, Grant County
Onshore wind · Harvest Wind LLC
20.0 MWWithdrawn / abandoned Grant, SDWest May 2009target 2011
Solar project X1-058A_DK2, Butler County
Solar
20.0 MWWithdrawn / abandoned Butler, OHPJM Apr 2011target 2012
Solar project AG2-607, King And Queen County
Solar · Cauthornville PV I, LLC
20.0 MWWithdrawn / abandoned King And Queen, VAPJM Mar 2021target 2023
Crown Point Solar
Solar + storage · Crown Point Solar LLC
20.0 MWWithdrawn / abandoned Essex, NYNYISO Aug 2024
Solar project AE1-038, Kent County
Solar
20.0 MWWithdrawn / abandoned Kent, DEPJM Jun 2018target 2020
Page 394 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)