United States βΊ Grid βΊ Interconnection queues βΊ North Carolina
SOLAR Β· PJMParnell Solar
Parnell Solar is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Martin County, North Carolina, connecting to Dominion.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2020 (completed)
- Withdrawn / abandonedNov 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG1-551
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Developer
- Parnell Solar, LLC
- Connection point (POI)
- Parmele 34.5 kV
- Location
- Martin County, North Carolina
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 30 September 2020
- Proposed online date
- October 2023
- Withdrawn
- November 2025
Location
Marker shows the centre of Martin County; the queue data does not give exact sites.
Power plants in North Carolina Β· Transmission lines in North Carolina
Other requests in Martin County
- Solar + storage project AH2-384, Martin CountySolar + storage Β· 10.0 MW Β· in study
- Domtar Paper Company Generating Units 7-10Other Β· 62.5 MW Β· built
- Williamston Speight SolarSolar Β· 15.0 MW Β· built
- Solar project AA2-157, Martin CountySolar Β· 80.0 MW Β· withdrawn
- Solar project AG2-120, Martin CountySolar Β· 21.0 MW Β· withdrawn
- Solar project AA2-029, Martin CountySolar Β· 8.0 MW Β· withdrawn
- Solar project AB2-098, Martin CountySolar Β· 5.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem