BATTERY STORAGE · NYISOChestertown BESS
Chestertown BESS is a 20.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Warren County, New York, connecting to NM-NG.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2020 (completed)
- Withdrawn / abandonedApr 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1101
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- Saturn Energy Storage LLC
- Connection point (POI)
- Chestertown-Warrensburg #6
- Location
- Warren County, New York
- Technology
- Battery: 20.0 MW
- Total requested
- 20.0 MW
- Queue status
- Withdrawn
- Entered queue
- 1 October 2020
- Withdrawn
- April 2021
Location
Marker shows the centre of Warren County; the queue data does not give exact sites.
Other requests in Warren County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem