🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 379

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 379 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Grand View Solar I
Solar · PD Solar 2 LLC
20.0 MWWithdrawn / abandoned Berks, PAPJM Sep 2021target 2024
Brookview Solar I
Solar
20.0 MWWithdrawn / abandoned Adams, PAPJM Apr 2018target 2025
Solar project W1-117, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2010target 2011
Chautauqua Solar
Solar · Northland Power U.S. Projects
20.0 MWWithdrawn / abandoned Chautauqua, NYNYISO Sep 2020
Other project 163, Jefferson County
Other
20.0 MWWithdrawn / abandoned Jefferson, ORWest Oct 2007target 2009
NY16 Solar
Solar · Boralex US Development, LLC
20.0 MWWithdrawn / abandoned Washington, NYNYISO May 2019
Onshore wind project 288, Teton County
Onshore wind
20.0 MWWithdrawn / abandoned Teton, MTWest Jun 2016target 2017
Solar project IC-629, Miller County
Solar
20.0 MWWithdrawn / abandoned Miller, GASoutheast Apr 2017
Solar project IC-505, Geneva County
Solar
20.0 MWWithdrawn / abandoned Geneva, ALSoutheast Sep 2016
Solar project IC-582, Macon County
Solar
20.0 MWWithdrawn / abandoned Macon, GASoutheast Jan 2017
Solar project AF2-017, Pike County
Solar
20.0 MWWithdrawn / abandoned Pike, KYPJM Oct 2019target 2021
Solar + storage project C4-098, Millard County
Solar + storage
20.0 MWWithdrawn / abandoned Millard, UTWest May 2024target 2027
Battery storage project AA2-104, Somerset County
Battery storage
20.0 MWWithdrawn / abandoned Somerset, PAPJM Apr 2015target 2016
Onshore wind project 155, Valley County
Onshore wind
20.0 MWWithdrawn / abandoned Valley, MTWest Aug 2012target 2013
Solar project Q200, Yavapai County
Solar
20.0 MWWithdrawn / abandoned Yavapai, AZWest Jun 2011target 2014
Solar project W1-087, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2010target 2011
Onshore wind project G658, Pope County
Onshore wind
20.0 MWWithdrawn / abandoned Pope, MNMISO Jul 2006target 2008
Summersweet Energy Center, LLC
Battery storage · Summersweet Energy Center, LLC
20.0 MWWithdrawn / abandoned Fauquier, VAPJM Feb 2025target 2023
Solar project GEN-2010-058, Chaves County
Solar
20.0 MWWithdrawn / abandoned Chaves, NMSPP Nov 2010target 2011
Other project 335, Ada County
Other
20.0 MWWithdrawn / abandoned Ada, IDWest Jun 2010
Battery storage project J749, Gratiot County
Battery storage
20.0 MWWithdrawn / abandoned Gratiot, MIMISO Nov 2016target 2018
Marshville Solar
Solar + storage · Naturgy Candela DevCo LLC
20.0 MWWithdrawn / abandoned Montgomery, NYNYISO May 2020
Solar project X2-005, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, PAPJM May 2011target 2012
Onshore wind project X1-014, Monroe County
Onshore wind
20.0 MWWithdrawn / abandoned Monroe, WVPJM Feb 2011target 2013
Solar project AF2-129, Mercer County
Solar
20.0 MWWithdrawn / abandoned Mercer, PAPJM Mar 2020target 2023
Solar + storage project AF2-034, Kendall County
Solar + storage · Kendall Solar BESS LLC
20.0 MWWithdrawn / abandoned Kendall, ILPJM Oct 2019target 2021
Solar project W1-075, Adams County
Solar
20.0 MWWithdrawn / abandoned Adams, PAPJM Apr 2010target 2012
Solar project SGI-PNM-2013-09, Santa Fe County
Solar
20.0 MWWithdrawn / abandoned Santa Fe, NMWest Dec 2013target 2016
Painted Hills IV
Onshore wind
20.0 MWWithdrawn / abandoned Riverside, CACAISO Oct 2008target 2010
Battery storage project AG2-532, Warren County
Battery storage · V20 Mansfield LLC
20.0 MWWithdrawn / abandoned Warren, NJPJM Mar 2025target 2022
Solar project 209, Kershaw County
Solar
20.0 MWWithdrawn / abandoned Kershaw, SCSoutheast Jun 2023target 2026
Onshore wind project G680, Yellow Medicine County
Onshore wind
20.0 MWWithdrawn / abandoned Yellow Medicine, MNMISO Sep 2006target 2008
Solar + storage project AH1-097, Carroll County
Solar + storage
20.0 MWWithdrawn / abandoned Carroll, VAPJM Jul 2021target 2025
Solar + storage project AG2-416, Crawford County
Solar + storage
20.0 MWWithdrawn / abandoned Crawford, PAPJM Mar 2021target 2025
Caprock Solar
Solar · OneEnergy Development, LLC
20.0 MWWithdrawn / abandoned Monroe, NYNYISO Jun 2016
Pivot Burnell BESS
Battery storage · Pivot Energy Development LLC
20.0 MWWithdrawn / abandoned Clinton, NYNYISO Aug 2022
Montross Solar
Solar
20.0 MWWithdrawn / abandoned Westmoreland, VAPJM Jul 2015target 2020
Solar + storage project AH1-422, Champaign County
Solar + storage
20.0 MWWithdrawn / abandoned Champaign, OHPJM Sep 2021target 2024
Solar project IC-478, Dooly County
Solar
20.0 MWWithdrawn / abandoned Dooly, GASoutheast Aug 2016
Solar project AF1-097, Centre County
Solar
20.0 MWWithdrawn / abandoned Centre, PAPJM Aug 2019target 2023
Solar project AF1-234, Berks County
Solar
20.0 MWWithdrawn / abandoned Berks, PAPJM Sep 2019target 2022
Solar project W3-163, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Oct 2010target 2011
Solar project AH1-622, York County
Solar
20.0 MWWithdrawn / abandoned York, PAPJM Sep 2021target 2025
Solar project Q156, Navajo County
Solar
20.0 MWWithdrawn / abandoned Navajo, AZWest Jun 2010target 2012
Thunderhill Solar Power
Solar
20.0 MWWithdrawn / abandoned Glenn, CACAISO Jul 2010target 2011
Greene County Energy
Solar · Greene County Energy Properties, LLC
20.0 MWWithdrawn / abandoned Greene, NYNYISO Sep 2016
Onshore wind project 353, Blaine County
Onshore wind
20.0 MWWithdrawn / abandoned Blaine, IDWest Aug 2010
Solar project Q148, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Jun 2010target 2012
Solar project 806, Klamath County
Solar
20.0 MWWithdrawn / abandoned Klamath, ORWest Sep 2016target 2019
Battery storage project AB1-075, Baltimore County
Battery storage
20.0 MWWithdrawn / abandoned Baltimore, MDPJM Sep 2015target 2016
Page 379 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)