United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

BATTERY STORAGE Β· MISO

Battery storage project J749, Gratiot County

Battery storage project J749, Gratiot County is a 20.0 MW battery storage request withdrawn in the MISO interconnection queue, in Gratiot County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2016 (completed)
  2. Withdrawn / abandonedMay 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J749
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Redstone 138 kV Substation
Location
Gratiot County, Michigan
Technology
Battery: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
14 November 2016
Proposed online date
September 2018
Withdrawn
May 2018

Location

Marker shows the centre of Gratiot County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Gratiot County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem