SOLAR Β· PJM

Solar project AF1-097, Centre County

Solar project AF1-097, Centre County is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Centre County, Pennsylvania, connecting to PENELEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2019 (completed)
  2. Withdrawn / abandonedSep 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AF1-097
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
Zion-E College Ave 34 kV
Location
Centre County, Pennsylvania
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
30 August 2019
Proposed online date
January 2023
Withdrawn
September 2019

Location

Marker shows the centre of Centre County; the queue data does not give exact sites.