Queue requests in study in the USA — page 33

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6,8521,550.1 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6,852 requests · page 33 of 138
ProjectCapacityStatusLocationRegionQueuedOnline
Excelsior Energy Center
Solar · Excelsior Energy Center, LLC
280 MWIn study Genesee, NYNYISO Jun 2018target 2026
Solar project AH2-342, Stark County
Solar
280 MWIn study Stark, ILPJM Mar 2022target 2027
Solar + storage project GEN-2024-015, Yoakum County
Solar + storage
280 MWIn study Yoakum, TXSPP Oct 2024target 2028
Battery storage project G0724, Curry County
Battery storage
280 MWIn study Curry, ORWest Jan 2022target 2026
Sandcut Storage
Solar + storage · Hoosier Energy / Solvenz
280 MWIn study Vigo, INMISO Dec 2025target 2028
Unicorn BESS
Battery storage · Unicorn Energies
279 MWIn study Fort Bend, TXERCOT Jan 2024target 2027
Onshore wind project G0994, Sherman County
Onshore wind
277 MWIn study Sherman, ORWest Nov 2023target 2028
Pease River Solar
Solar · Pease River Solar LLC
276 MWIn study Foard, TXERCOT Dec 2025target 2029
Blue Hills Wind
Onshore wind
276 MWPaused / redesign Val Verde, TXERCOT May 2019target 2026
Gas project 636, Humphreys County
Gas
276 MWIn study Humphreys, TNSoutheast Jul 2024target 2028
Solar + storage project PIS047, Juab County
Solar + storage
275 MWIn study Juab, UTWest Dec 2023target 2027
Solar project 923973, Richmond County
Solar · Masked
275 MWIn study Richmond, NCSoutheast Sep 2023
Other project Q582, Maricopa County
Other
275 MWIn study Maricopa, AZWest May 2025target 2030
Other project PP00046, Richmond County
Other
275 MWIn study Richmond, NCSoutheast Aug 2025target 2029
Solar + storage project Q362, Pinal County
Solar + storage
275 MWIn study Pinal, NCWest Sep 2020target 2023
Solar + storage project GEN-2024-166, Sedgwick County
Solar + storage
275 MWIn study Sedgwick, KSSPP Mar 2025target 2030
Onshore wind project J3564, Newton County
Onshore wind
275 MWIn study Newton, INMISO Apr 2024target 2028
Solar + storage project 26, Sacramento County
Solar + storage
275 MWIn study Sacramento, CAWest Sep 2022target 2030
Solar + storage project T2-023, Juab County
Solar + storage
275 MWIn study Juab, UTWest Sep 2025target 2026
Onshore wind project J3846, Newton County
Onshore wind
275 MWIn study Newton, INMISO Jan 2025target 2030
Gas project GEN-2023-079, Cass County
Gas
273 MWIn study Cass, NESPP Oct 2023target 2032
Roboman Solar
Solar · Roboman Solar, LLC
273 MWIn study Coke, TXERCOT Jul 2025target 2029
Solar project AI2-081, Logan County
Solar
271 MWIn study Logan, OHPJM Feb 2023target 2025
Gas project AH1-734, Indiana County
Gas · Armstrong Power, LLC
270 MWIn study Indiana, PAPJM Apr 2025
Solar + storage project 119, Greenlee County
Solar + storage
270 MWIn study Greenlee, AZWest Apr 2022target 2027
Solar + storage project GEN-2024-035, Brown County
Solar + storage
270 MWIn study Brown, SDSPP Oct 2024target 2027
Nuclear project G0919, Benton County
Nuclear
270 MWIn study Benton, WAWest Aug 2023target 2031
Solar project J1890, Sabine Parish County
Solar
270 MWIn study Sabine Parish, LAMISO Apr 2025target 2027
Solar + storage project Q392, Pinal County
Solar + storage
270 MWIn study Pinal, AZWest Mar 2021target 2024
Solar + storage project GI-2022-162, Imperial County
Solar + storage
270 MWIn study Imperial, CAWest Sep 2022target 2026
Solar project J3986, Liberty County
Solar
270 MWIn study Liberty, TXMISO Oct 2024target 2030
South Ripley Solar and BESS
Solar + storage · ConnectGen Chautauqua County LLC
270 MWIn study Chautauqua, NYNYISO Dec 2018target 2027
Solar project GEN-2022-015, Decatur County
Solar
270 MWIn study Decatur, KSSPP Jun 2022target 2028
Gas project GEN-2024-023, Gage County
Gas
270 MWIn study Gage, NESPP Oct 2024target 2030
Shoestring
Solar + storage
270 MWIn study Fresno, CACAISO Apr 2023target 2031
Madison County Combustion Turbine
Gas · Indiana Municipal Power Agency (IMPA)
268 MWIn study Anderson, INMISO Aug 2025target 2028
Geras
Solar + storage
268 MWIn study Stanislaus, CACAISO Apr 2023target 2028
Gas project E0034, Brookings County
Gas · Basin Electric Power Cooperative
265 MWIn study Brookings, SDMISO Aug 2025target 2027
Orient Energy Center
Gas · MidAmerican Energy Company
265 MWIn study Adair, IAMISO Aug 2025target 2027
Solar project J2565, Iroquois County
Solar
265 MWIn study Iroquois, ILMISO Sep 2022target 2026
Gas project FC100382, Osceola County
Gas · Duke Energy Florida, LLC
265 MWIn study Osceola, FLSoutheast Dec 2025target 2030
Santa Garcias Solar
Solar · Oxy Renewable Energy LLC
265 MWIn study Kleberg, TXERCOT Jun 2023target 2028
Gas project FC100386, Osceola County
Gas · Duke Energy Florida, LLC
265 MWIn study Osceola, FLSoutheast Dec 2025target 2030
Wind + storage project GEN-2024-278, Lea County
Wind + storage
264 MWIn study Lea, NMSPP Mar 2025target 2029
Battery storage project Q2510, Maricopa County
Battery storage
264 MWIn study Maricopa, AZWest Feb 2025target 2028
Battery storage project GEN-2025-SR28, Beaver County
Battery storage
263 MWIn study Beaver, OKSPP Aug 2025target 2027
Surplus; J500
Gas
263 MWIn study Adair, IAMISO Jul 2025target 2027
Gas project J3047, Adair County
Gas
263 MWIn study Adair, IAMISO Sep 2022target 2027
Onshore wind project J3313, Lenawee County
Onshore wind
263 MWIn study Lenawee, MIMISO Apr 2024target 2028
Gas project J2791, Lafayette Parish County
Gas
263 MWIn study Lafayette Parish, LAMISO Sep 2022target 2027
Page 33 of 138

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)