United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2022 requests) โ€” page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,886378.9 GW
Active in queue299.4 GW1,514 requests
Agreement signed43.0 GW228 requests
Withdrawn1,886378.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,886 requests ยท page 3 of 38
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project Q481, Maricopa County
Solar
550 MWWithdrawn / abandoned Maricopa, AZWest Sep 2022target 2026
Battery storage project Q24, Pinal County
Battery storage
533 MWWithdrawn / abandoned Pinal, AZWest Sep 2022target 2026
OFFERED Combined Cycle Gen
Gas ยท Blue Cube Operations
520 MWWithdrawn / abandoned Brazoria, TXERCOT Dec 2022target 2025
Onshore wind project C2-34, Carbon County
Onshore wind
506 MWWithdrawn / abandoned Carbon, WYWest Apr 2022target 2024
Ventana Ranch Solar
Solar ยท Monarch Energy Development LLC
502 MWWithdrawn / abandoned ERCOT Nov 2022target 2026
Green Bird Solar
Solar ยท Gigawatt Solar LLC
502 MWWithdrawn / abandoned Johnson, TXERCOT Feb 2022target 2024
Onshore wind project C2-108, Sweetwater County
Onshore wind
500 MWWithdrawn / abandoned Sweetwater, WYWest May 2022target 2025
Solar + storage project Q491, Yuma County
Solar + storage
500 MWWithdrawn / abandoned Yuma, AZWest Sep 2022target 2026
Solar + storage project IA-PNM-2022-08, Curry County
Solar + storage
500 MWWithdrawn / abandoned Curry, NMWest Apr 2022target 2025
Solar + storage project Company PI, Humboldt County
Solar + storage
500 MWWithdrawn / abandoned Humboldt, NVWest Mar 2022target 2029
Other project J2697, St. Clair County
Other
500 MWWithdrawn / abandoned St. Clair, ILMISO Sep 2022target 2027
Solar + storage project Company NN, Storey County
Solar + storage
500 MWWithdrawn / abandoned Storey, NVWest Mar 2022target 2025
Fresh Kills Energy Storage
Battery storage ยท Fresh Kills Battery Storage LLC
500 MWWithdrawn / abandoned Richmond, NYNYISO Mar 2022
Solar project J2785, Calhoun County
Solar
500 MWWithdrawn / abandoned Calhoun, ARMISO Sep 2022target 2026
Onshore wind project J2698, Choctaw County
Onshore wind
500 MWWithdrawn / abandoned Choctaw, MSMISO Sep 2022target 2028
Solar project GEN-2022-076, Stevens County
Solar
500 MWWithdrawn / abandoned Stevens, KSSPP Sep 2022target 2026
Battery storage project C2-24, Grant County
Battery storage ยท PacifiCorp
500 MWWithdrawn / abandoned Grant, WAWest Apr 2022target 2028
Solar project J2758, Jefferson County
Solar
500 MWWithdrawn / abandoned Jefferson, ARMISO Sep 2022target 2025
Wind
Onshore wind
500 MWWithdrawn / abandoned Aroostook, MEISO-NE Jan 2022target 2025
Solar + storage project Q03, Maricopa County
Solar + storage
500 MWWithdrawn / abandoned Maricopa, AZWest May 2022target 2025
Sprain Brook Energy Storage
Battery storage ยท Yonkers Renewable Energy LLC
500 MWWithdrawn / abandoned Westchester, NYNYISO Mar 2022
Solar + storage project 2022-G2
Solar + storage
500 MWWithdrawn / abandoned West Mar 2022target 2025
Goethals Energy Storage Project
Battery storage ยท Staten Island Power LLC
500 MWWithdrawn / abandoned Richmond, NYNYISO Mar 2022
Solar project J2706, Morehouse Parish County
Solar
500 MWWithdrawn / abandoned Morehouse Parish, LAMISO Sep 2022target 2027
Battery storage project J2443, Kosciusko County
Battery storage
500 MWWithdrawn / abandoned Kosciusko, INMISO Sep 2022target 2025
Other project J2692, Choctaw County
Other
500 MWWithdrawn / abandoned Choctaw, MSMISO Sep 2022target 2028
Onshore wind project C2-107, Sweetwater County
Onshore wind
500 MWWithdrawn / abandoned Sweetwater, WYWest May 2022target 2025
Solar project J2399, Craighead County
Solar
500 MWWithdrawn / abandoned Craighead, ARMISO Sep 2022target 2025
Solar project J3032, Webster Parish County
Solar
500 MWWithdrawn / abandoned Webster Parish, LAMISO Sep 2022target 2026
Battery storage project C2-20, Sanpete County
Battery storage ยท PacifiCorp
500 MWWithdrawn / abandoned Sanpete, UTWest Apr 2022target 2028
Buchanan Energy Storage-South
Battery storage ยท Peekskill BESS LLC
500 MWWithdrawn / abandoned Westchester, NYNYISO Apr 2022
Solar + storage project Q492, Pinal County
Solar + storage
500 MWWithdrawn / abandoned Pinal, AZWest Sep 2022target 2026
Solar + storage project 674, Ada County
Solar + storage
500 MWWithdrawn / abandoned Ada, IDWest Oct 2022
Battery storage project C2-25, Lincoln County
Battery storage ยท PacifiCorp
500 MWWithdrawn / abandoned Lincoln, WYWest Apr 2022target 2028
Solar project J2888, Lafayette Parish County
Solar
500 MWWithdrawn / abandoned Lafayette Parish, LAMISO Sep 2022target 2026
Diamond Solar
Solar ยท Hecate Energy Diamond Solar LLC
500 MWWithdrawn / abandoned Herkimer, NYNYISO Mar 2022
Battery storage project C2-17, Converse County
Battery storage ยท PacifiCorp
500 MWWithdrawn / abandoned Converse, WYWest Apr 2022target 2028
Battery storage project C2-18, Klamath County
Battery storage ยท PacifiCorp
500 MWWithdrawn / abandoned Klamath, ORWest Apr 2022target 2028
Battery storage project C2-26, Lake County
Battery storage ยท PacifiCorp
500 MWWithdrawn / abandoned Lake, ORWest Apr 2022target 2028
Solar + storage project 694, Canyon County
Solar + storage
500 MWWithdrawn / abandoned Canyon, IDWest Dec 2022
Dark Lark BESS
Other
500 MWWithdrawn / abandoned Henderson, TXERCOT Jun 2022
Battery storage project C2-23, Converse County
Battery storage ยท PacifiCorp
500 MWWithdrawn / abandoned Converse, WYWest Apr 2022target 2028
Solar + storage project 671, Lincoln County
Solar + storage
500 MWWithdrawn / abandoned Lincoln, IDWest Oct 2022
Battery storage project Q452, Maricopa County
Battery storage
500 MWWithdrawn / abandoned Maricopa, AZWest Mar 2022target 2025
Solar + storage project J3106, Pemiscot County
Solar + storage
500 MWWithdrawn / abandoned Pemiscot, MOMISO Sep 2022target 2025
Onshore wind project PIS004, Carbon County
Onshore wind
500 MWWithdrawn / abandoned Carbon, WYWest Apr 2022target 2025
Solar project J2682, Jackson County
Solar
500 MWWithdrawn / abandoned Jackson, ARMISO Sep 2022target 2025
Solar project J2452, Cleveland County
Solar
500 MWWithdrawn / abandoned Cleveland, ARMISO Sep 2022target 2026
Battery storage project C2-22, Emery County
Battery storage ยท PacifiCorp
500 MWWithdrawn / abandoned Emery, UTWest Apr 2022target 2028
Wind
Onshore wind
500 MWWithdrawn / abandoned Aroostook, MEISO-NE Jan 2022target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)