SOLAR + STORAGE Β· WEST

Solar + storage project 2022-G2

Solar + storage project 2022-G2 is a 500 MW solar + storage request withdrawn in the West interconnection queue, connecting to WAPA Rocky Mountain Region.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2022-G2
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA Rocky Mountain Region
Connection point (POI)
Glen Canyon - Flagstaff
Technology
Solar: 500 MW Β· Battery
Total requested
500 MW
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
1 March 2022
Proposed online date
December 2025

Location

No county location in the queue data.

Power plants in Β· Transmission lines in