United States βΊ Grid βΊ Interconnection queues
SOLAR Β· ERCOTVentana Ranch Solar
Ventana Ranch Solar is a 502 MW solar request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2022 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 24INR0462
- Grid region
- ERCOT (Texas)
- Developer
- Monarch Energy Development LLC
- Connection point (POI)
- Tap 345 kV Lon Hill (Bus# 8455) -- North Edinburg (Bus# 8905)
- Technology
- Solar: 502 MW
- Total requested
- 502 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 15 November 2022
- Proposed online date
- December 2026
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem