United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2021 requests) โ€” page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,149339.1 GW
Active in queue227.7 GW896 requests
Agreement signed73.3 GW270 requests
Withdrawn2,149339.1 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,149 requests ยท page 3 of 43
ProjectCapacityStatusLocationRegionQueuedOnline
Fuerte Energy Storage
Battery storage
554 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2024
Alum Geothermal
Geothermal
530 MWWithdrawn / abandoned Esmeralda, NVCAISO Apr 2021target 2025
Appellation
Battery storage
515 MWWithdrawn / abandoned CACAISO Apr 2021target 2024
MT Baldy Energy Storage
Battery storage
513 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2031
Menilles
Solar + storage
511 MWWithdrawn / abandoned Fresno, CACAISO Apr 2021target 2024
Blythe BESS
Battery storage
510 MWWithdrawn / abandoned Riverside, CACAISO Mar 2021target 2022
Goodall Storage
Battery storage
510 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2023
Amsterdam Solar II
Solar ยท Cottonwood Bayou Solar II, LLC
510 MWWithdrawn / abandoned Brazoria, TXERCOT Aug 2021target 2026
Dolores
Battery storage
510 MWWithdrawn / abandoned San Clara, CACAISO Apr 2021target 2025
Winoka Hybrid Solar
Solar + storage
508 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2024
Stirling Bridge
Solar + storage
507 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2021target 2031
Bison Peak
Battery storage
506 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2025
Ada Energy Storage
Battery storage
505 MWWithdrawn / abandoned Santa Clara, CACAISO Apr 2021target 2034
Spindle Energy Storage
Battery storage
504 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2021target 2024
Commander Energy Storage
Battery storage
504 MWWithdrawn / abandoned Contra Costa, CACAISO Apr 2021target 2032
Moonstone Energy Storage
Battery storage
504 MWWithdrawn / abandoned Alameda, CACAISO Apr 2021target 2024
Onshore wind project Q73, Apache County
Onshore wind
500 MWWithdrawn / abandoned Apache, AZWest Apr 2021target 2028
Solar + storage project Q428, Navajo County
Solar + storage
500 MWWithdrawn / abandoned Navajo, AZWest Sep 2021target 2024
Onshore wind project GI-2021-19, Pueblo County
Onshore wind
500 MWWithdrawn / abandoned Pueblo, COWest Sep 2021target 2025
Solar + storage project Q417, Coconino County
Solar + storage
500 MWWithdrawn / abandoned Coconino, AZWest Sep 2021target 2024
Solar + storage project Q79, Pinal County
Solar + storage
500 MWWithdrawn / abandoned Pinal, AZWest May 2021target 2025
Onshore wind project J1893, Morton County
Onshore wind
500 MWWithdrawn / abandoned Morton, NDMISO Nov 2021target 2024
Onshore wind project Q418, Coconino County
Onshore wind
500 MWWithdrawn / abandoned Coconino, AZWest Sep 2021target 2024
Solar project J2086, Barnes County
Solar
500 MWWithdrawn / abandoned Barnes, NDMISO Aug 2021target 2025
Onshore wind project GI-2021-20, Pueblo County
Onshore wind
500 MWWithdrawn / abandoned Pueblo, COWest Sep 2021target 2025
Solar + storage project Q430, Coconino County
Solar + storage
500 MWWithdrawn / abandoned Coconino, AZWest Sep 2021target 2024
Solar project AG2-655, Grant County
Solar ยท Mount Storm Solar, LLC
500 MWWithdrawn / abandoned Grant, WVPJM Mar 2021target 2024
Solar project GI-2021-30, Morgan County
Solar
500 MWWithdrawn / abandoned Morgan, COWest Oct 2021target 2024
Battery storage project AG2-375, Hancock County
Battery storage ยท Foster Energy Storage LLC
500 MWWithdrawn / abandoned Hancock, OHPJM Mar 2021target 2024
Solar + storage project Q416, Pinal County
Solar + storage
500 MWWithdrawn / abandoned Pinal, AZWest Sep 2021target 2024
Solar + storage project Company MF, Humboldt County
Solar + storage
500 MWWithdrawn / abandoned Humboldt, NVWest Sep 2021target 2024
Battery storage project AG2-475, Charles City County
Battery storage
500 MWWithdrawn / abandoned Charles City, VAPJM Mar 2021target 2024
Solar project GEN-2021-074, Prowers County
Solar
500 MWWithdrawn / abandoned Prowers, COSPP May 2021target 2026
Gwent Storage 2
Battery storage
473 MWWithdrawn / abandoned Ventura, CACAISO Apr 2021target 2033
Salvador
Solar + storage
470 MWWithdrawn / abandoned Riverside, CACAISO Apr 2021target 2030
Battery storage project Q84, Maricopa County
Battery storage
463 MWWithdrawn / abandoned Maricopa, AZWest Oct 2021target 2025
Velas
Battery storage
463 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2021target 2031
Offshore wind project AG2-108, Sussex County
Offshore wind
460 MWWithdrawn / abandoned Sussex, DEPJM Jan 2021target 2026
Solar + storage project G0682, Klickitat County
Solar + storage
459 MWWithdrawn / abandoned Klickitat, WAWest Jul 2021target 2025
Ponta Power Station
Gas ยท WattBridge Energy, LLC
459 MWWithdrawn / abandoned Cherokee, TXERCOT Feb 2021target 2024
Onshore wind project MPC04300, Steele County
Onshore wind
457 MWWithdrawn / abandoned Steele, NDMISO Jul 2021target 2024
Bull Run
Solar + storage
457 MWWithdrawn / abandoned Butte, CACAISO Apr 2021target 2030
Onshore wind project C1-32, Millard County
Onshore wind
456 MWWithdrawn / abandoned Millard, UTWest May 2021target 2024
Longmeadow Hybrid Solar
Solar + storage
456 MWWithdrawn / abandoned Riverside, CACAISO Apr 2021target 2024
Solar + storage project AH1-645, Isle Of Wight County
Solar + storage
450 MWWithdrawn / abandoned Isle Of Wight, VAPJM Sep 2021target 2025
Gas project GEN-2021-095, Mercer County
Gas
447 MWWithdrawn / abandoned Mercer, NDSPP Apr 2021target 2028
Gas project GEN-2021-094, Mercer County
Gas
447 MWWithdrawn / abandoned Mercer, NDSPP Apr 20212025
Offshore wind
Offshore wind
440 MWWithdrawn / abandoned MAISO-NE Aug 2021target 2026
Offshore wind project AG2-342, Sussex County
Offshore wind
440 MWWithdrawn / abandoned Sussex, DEPJM Mar 2021target 2026
Gilmore Solar
Solar + storage
430 MWWithdrawn / abandoned Tulare, CACAISO Apr 2021target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)