Solar + storage project G0682, Klickitat County

Solar + storage project G0682, Klickitat County is a 459 MW solar + storage request withdrawn in the West interconnection queue, in Klickitat County, Washington.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2021 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G0682
Grid region
West (non-ISO utilities)
Connection point (POI)
Big Eddy - Spring Creek No 1 230 kV line, approximately 28 miles NE of the Big Eddy Substation
Location
Klickitat County, Washington
Technology
Solar: 305 MW Β· Battery: 154 MW
Total requested
459 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
13 July 2021
Proposed online date
December 2025

Location

Marker shows the centre of Klickitat County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington