SOLAR + STORAGE · CAISO

Gilmore Solar

Gilmore Solar is a 430 MW solar + storage request withdrawn in the CAISO interconnection queue, in Tulare County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedSep 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2063
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Vestal Substation 230 kV
Location
Tulare County, California
Technology
Solar: 215 MW · Battery: 215 MW
Total requested
430 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
15 April 2021
Proposed online date
October 2025
Withdrawn
September 2021

Location

Marker shows the centre of Tulare County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Tulare County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem