United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in the USA (2024 requests) β€” page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown11730.3 GW
Active in queue285.2 GW1,283 requests
Agreement signed30.3 GW117 requests
Withdrawn1,313251.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

117 requests Β· page 3 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project IC-1267, Floyd County
Battery storage
57.5 MWAgreement signed Floyd, GASoutheast Mar 2024target 2026
AN50B
Battery storage
50.0 MWAgreement signed Luna, NMWest Mar 2024target 2027
Solar project CS24-14, Spokane County
Solar
40.0 MWAgreement signed Spokane, WAWest Apr 2024target 2028
Battery storage project GEN-2024-SR14, Lea County
Battery storage
36.0 MWAgreement signed Lea, NMSPP Jul 2024target 2026
Other project GEN-2024-GR4, Cherokee County
Other
27.1 MWAgreement signed Cherokee, KSSPP Jul 2024target 2026
Battery storage project IC-1280, Floyd County
Battery storage
15.0 MWAgreement signed Floyd, GASoutheast Apr 2024target 2027
Empire Central BESS
Battery storage Β· SMT Dallas III LLC
10.0 MWAgreement signed Dallas, TXERCOT Jan 2024target 2025
Carrizo Springs BESS
Battery storage Β· Regis Carrizo Springs LLC
10.0 MWAgreement signed Dimmit, TXERCOT Aug 20242025
Poteet BESS
Battery storage Β· HEN INFRASTRUCTURE, LLC 1
10.0 MWAgreement signed Atascosa, TXERCOT Oct 2024target 2026
Lantana BESS
Battery storage Β· Aggreko MSR Grid PC2
10.0 MWAgreement signed Nueces, TXERCOT Apr 2024target 2026
Abilene Elmcreek BESS
Battery storage Β· DGSP2 LLC
9.9 MWAgreement signed Taylor, TXERCOT Sep 2024target 2026
Abilene Industrial Park BESS
Battery storage Β· Distributed Generation Solutions LLC
9.9 MWAgreement signed Taylor, TXERCOT Sep 2024target 2026
Cedarvale Gas
Gas Β· RPC Merchant LLC
9.9 MWAgreement signed Ward, TXERCOT Oct 2024target 2026
Solar project 752, Malheur County
Solar Β· Fry Foods Inc.
4.2 MWAgreement signed Malheur, ORWest Aug 2024target 2025
Solar project CS24-07, Adams County
Solar
2.0 MWAgreement signed Adams, WAWest Apr 2024target 2026
Solar project CS24-01, Adams County
Solar
1.0 MWAgreement signed Adams, WAWest Mar 2024target 2024
Battery storage project CS24-02, Spokane County
Battery storage
0.5 MWAgreement signed Spokane, WAWest Apr 2024target 2025
Page 3 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)