Withdrawn queue requests in SPP (Southwest Power Pool) — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,846382.9 GW
Active in queue152.4 GW692 requests
Agreement signed37.6 GW212 requests
Withdrawn1,846382.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,846 requests · page 3 of 37
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2018-044, Antelope County
Solar
500 MWWithdrawn / abandoned Antelope, NESPP May 20182025
Solar project GEN-2020-085, Carter County
Solar
500 MWWithdrawn / abandoned Carter, OKSPP Apr 2020target 2026
Solar + storage project GEN-2024-302, Roosevelt County
Solar + storage
500 MWWithdrawn / abandoned Roosevelt, NMSPP Mar 2025target 2029
Onshore wind project GEN-2023-116, Keith County
Onshore wind
500 MWWithdrawn / abandoned Keith, NESPP Oct 2023target 2030
Solar project GEN-2022-076, Stevens County
Solar
500 MWWithdrawn / abandoned Stevens, KSSPP Sep 2022target 2026
Solar project GEN-2020-086, Butler County
Solar
500 MWWithdrawn / abandoned Butler, KSSPP Apr 2020target 2026
Solar project GEN-2018-005, Haskell County
Solar
500 MWWithdrawn / abandoned Haskell, OKSPP Apr 2018target 2021
Onshore wind project GEN-2024-199, Chaves County
Onshore wind
500 MWWithdrawn / abandoned Chaves, NMSPP Mar 2025target 2028
Solar project GEN-2019-007, Lancaster County
Solar
500 MWWithdrawn / abandoned Lancaster, NESPP Apr 2019target 2022
Gas project GEN-2000-009, Mccurtain County
Gas
500 MWWithdrawn / abandoned Mccurtain, OKSPP
Solar + storage project GEN-2024-301, Roosevelt County
Solar + storage
500 MWWithdrawn / abandoned Roosevelt, NMSPP Mar 2025target 2029
Onshore wind project GEN-2024-198, Chaves County
Onshore wind
500 MWWithdrawn / abandoned Chaves, NMSPP Mar 2025target 2028
Onshore wind project GEN-2023-237, Hale County
Onshore wind
500 MWWithdrawn / abandoned Hale, TXSPP Oct 2023target 2030
Onshore wind project GEN-2018-110, Nemaha County
Onshore wind
500 MWWithdrawn / abandoned Nemaha, NESPP Nov 2018target 2023
Gas project GEN-2001-004, Curry County
Gas
500 MWWithdrawn / abandoned Curry, NMSPP Jan 2001
Onshore wind project GEN-2022-059, Stevens County
Onshore wind
500 MWWithdrawn / abandoned Stevens, KSSPP Jun 20222025
Gas project GEN-2001-008, Ector County
Gas
500 MWWithdrawn / abandoned Ector, TXSPP Mar 2001
Solar project GEN-2021-074, Prowers County
Solar
500 MWWithdrawn / abandoned Prowers, COSPP May 2021target 2026
Onshore wind project GEN-2008-048, Kiowa County
Onshore wind
500 MWWithdrawn / abandoned Kiowa, COSPP May 2008target 2011
Onshore wind project GEN-2008-112, Harper County
Onshore wind
500 MWWithdrawn / abandoned Harper, OKSPP Sep 2008target 2011
Gas project GEN-2024-012, Oklahoma County
Gas
496 MWWithdrawn / abandoned Oklahoma, OKSPP Aug 2024target 2029
Other project GEN-2017-062, Beaver County
Other
488 MWWithdrawn / abandoned Beaver, OKSPP May 2017target 2022
Gas project GEN-2014-017, Nacogdoches County
Gas
477 MWWithdrawn / abandoned Nacogdoches, TXSPP Jun 2014target 2018
Onshore wind project GEN-2017-135, Oklahoma County
Onshore wind
470 MWWithdrawn / abandoned Oklahoma, OKSPP Nov 2017target 2020
Onshore wind project GEN-2009-022, Rawlins County
Onshore wind
468 MWWithdrawn / abandoned Rawlins, KSSPP Jun 2009target 2011
Gas project GEN-2015-050, Lyon County
Gas
464 MWWithdrawn / abandoned Lyon, KSSPP Oct 2015target 2019
Solar project GEN-2024-307, Houston County
Solar
455 MWWithdrawn / abandoned Houston, TXSPP Mar 2025target 2028
Gas project GEN-2024-053, Nodaway County
Gas
451 MWWithdrawn / abandoned Nodaway, MOSPP Oct 2024target 2032
Gas project GEN-2024-028, Nodaway County
Gas
451 MWWithdrawn / abandoned Nodaway, MOSPP Oct 2024target 2030
Onshore wind project GEN-2010-029, Ford County
Onshore wind
450 MWWithdrawn / abandoned Ford, KSSPP May 2010target 2013
Onshore wind project GEN-2017-114, Dewey County
Onshore wind
450 MWWithdrawn / abandoned Dewey, SDSPP Oct 2017target 2021
Gas project GEN-2021-095, Mercer County
Gas
447 MWWithdrawn / abandoned Mercer, NDSPP Apr 2021target 2028
Gas project GEN-2021-094, Mercer County
Gas
447 MWWithdrawn / abandoned Mercer, NDSPP Apr 20212025
Solar project GEN-2024-GR2, Chouteau County
Solar
442 MWWithdrawn / abandoned Chouteau, OKSPP Feb 2024target 2026
Onshore wind project GEN-2016-159, Stanton County
Onshore wind
428 MWWithdrawn / abandoned Stanton, NESPP Nov 2016target 2020
Onshore wind project GEN-2023-114, Lamoure County
Onshore wind
425 MWWithdrawn / abandoned Lamoure, NDSPP Oct 2023target 2030
Gas project GEN-2012-014, Gray County
Gas
425 MWWithdrawn / abandoned Gray, TXSPP Jun 2012target 2015
Gas project GEN-2020-024, Sarpy County
Gas
425 MWWithdrawn / abandoned Sarpy, NESPP Apr 20202023
Gas project GEN-2020-035, Cass County
Gas
425 MWWithdrawn / abandoned Cass, NESPP Apr 20202023
Onshore wind project GEN-2009-042, Roger Mills County
Onshore wind
414 MWWithdrawn / abandoned Roger Mills, OKSPP Sep 2009target 2012
Onshore wind project GEN-2019-029, Keith County
Onshore wind
404 MWWithdrawn / abandoned Keith, NESPP Apr 20192024
Onshore wind project GEN-2021-071, Noble County
Onshore wind
403 MWWithdrawn / abandoned Noble, OKSPP Apr 2021target 2027
Onshore wind project GEN-2024-103, Finney County
Onshore wind
401 MWWithdrawn / abandoned Finney, KSSPP Mar 2025target 2031
Onshore wind project GEN-2016-120, Crosby County
Onshore wind
400 MWWithdrawn / abandoned Crosby, TXSPP Nov 2016target 2020
Coal project GEN-2007-011N01, Lancaster County
Coal
400 MWWithdrawn / abandoned Lancaster, NESPP Mar 2007
Coal project GEN-2001-039N, Hall County
Coal
400 MWWithdrawn / abandoned Hall, NESPP Nov 2001
Solar project GEN-2018-066, Lancaster County
Solar
400 MWWithdrawn / abandoned Lancaster, NESPP Oct 2018target 2022
Onshore wind project GEN-2016-044, Logan County
Onshore wind
400 MWWithdrawn / abandoned Logan, NDSPP Mar 20162018
Wind + storage project GEN-2022-177, Hamilton County
Wind + storage
400 MWWithdrawn / abandoned Hamilton, KSSPP Feb 2023target 2027
Onshore wind project GEN-2024-222, Roosevelt County
Onshore wind
400 MWWithdrawn / abandoned Roosevelt, NMSPP Mar 2025target 2030
Page 3 of 37

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)