United States βΊ Grid βΊ Interconnection queues βΊ New Mexico
SOLAR + STORAGE Β· SPPSolar + storage project GEN-2024-301, Roosevelt County
Solar + storage project GEN-2024-301, Roosevelt County is a 500 MW solar + storage request withdrawn in the SPP interconnection queue, in Roosevelt County, New Mexico, connecting to SPS.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2025 (completed)
- Withdrawn / abandonedDec 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2024-301
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- Crossroads 345 kV Substation
- Location
- Roosevelt County, New Mexico
- Technology
- Solar: 500 MW Β· Battery
- Total requested
- 500 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 1 March 2025
- Proposed online date
- December 2029
- Withdrawn
- December 2025
Location
Marker shows the centre of Roosevelt County; the queue data does not give exact sites.
Power plants in New Mexico Β· Transmission lines in New Mexico
Other requests in Roosevelt County
- Solar project GEN-2019-003, Roosevelt CountySolar Β· 150 MW Β· agreement signed
- Solar project GEN-2019-021, Roosevelt CountySolar Β· 50.0 MW Β· agreement signed
- Solar + storage project GEN-2024-303, Roosevelt CountySolar + storage Β· 500 MW Β· in study
- Solar + storage project GEN-2024-304, Roosevelt CountySolar + storage Β· 500 MW Β· in study
- Onshore wind project GEN-2024-221, Roosevelt CountyOnshore wind Β· 400 MW Β· in study
- Solar project GEN-2024-159, Roosevelt CountySolar Β· 300 MW Β· in study
- Solar + storage project ERAS-2025-018, Roosevelt CountySolar + storage Β· 256 MW Β· in study
- Onshore wind project GEN-2024-043, Roosevelt CountyOnshore wind Β· 250 MW Β· in study
- Battery storage project GEN-2024-092, Roosevelt CountyBattery storage Β· 200 MW Β· in study
- Solar project IA-PNM-2023-16, Roosevelt CountySolar Β· 199 MW Β· in study
- Onshore wind project GEN-2025-GR2, Roosevelt CountyOnshore wind Β· 120 MW Β· in study
- Battery storage project IA-PNM-2024-01, Roosevelt CountyBattery storage Β· 100 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem