United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in the USA — page 273
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project IC-939, Covington County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-885, Dallas County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project 569086, Jones County Solar |
80.0 MW | Withdrawn / abandoned |
| PV-31 Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 962986, Jones County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 46, Pima County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-751, Shelby County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-838, Shelby County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-576, Clarke County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-782, Clarke County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2014-053, Hockley County Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Onshore wind project J883, Pulaski County Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Surplus; J1294 Other |
80.0 MW | Withdrawn / abandoned |
| Battery storage project GEN-2022-064, Major County Battery storage |
80.0 MW | Withdrawn / abandoned |
| Solar project J2257, Evangeline Parish County Solar |
80.0 MW | Withdrawn / abandoned |
| Onshore wind project 18-07261, Larimer County Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Solar project 541, San Juan County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 357, Jackson County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-443, Perry County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project AD2-183, Bertie County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Cameron Wind Onshore wind · Cielo Wind Power |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-568, Baldwin County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 569144, Duplin County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project C2-185, Lake County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project C3-020, Albany County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project GEN-2018-084, Linn County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project TCS-17, Rich County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project J3205, Franklin County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-721, Baldwin County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-1007, Lowndes County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 591, Juab County Solar |
80.0 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2003-017, Dallam County Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-763, Greene County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project 66, Pima County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-1076, Montgomery County Solar |
80.0 MW | Withdrawn / abandoned |
| Onshore wind project AD1-069, Fayette County Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Honey Ridge Solar Solar · Honey Ridge Solar 1 |
80.0 MW | Withdrawn / abandoned |
| Solar project GI-2017-9, Pueblo County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project GEN-2014-043, Gaines County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-633, Appling County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project Company IM, Washoe County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project Q48, Pinal County Solar |
80.0 MW | Withdrawn / abandoned |
| Battery storage project C2-133, Juab County Battery storage |
80.0 MW | Withdrawn / abandoned |
| Solar project J1173, Lenawee County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-1151, Lowndes County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project 2021-G3 Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-741, Tuscaloosa County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Freeport Wind Farm Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Solar project G0557, Lake County Solar |
80.0 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2009-003O, Otoe County Onshore wind |
80.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)