United States β€Ί Grid β€Ί Interconnection queues β€Ί Wyoming

SOLAR + STORAGE Β· WEST

Solar + storage project C3-020, Albany County

Solar + storage project C3-020, Albany County is a 80.0 MW solar + storage request withdrawn in the West interconnection queue, in Albany County, Wyoming, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
C3-020
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Ft. Sanders substation
Location
Albany County, Wyoming
Technology
Solar: 80.0 MW Β· Battery
Total requested
80.0 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
28 April 2023
Proposed online date
December 2026

Location

Marker shows the centre of Albany County; the queue data does not give exact sites.

Power plants in Wyoming Β· Transmission lines in Wyoming

Other requests in Albany County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem